BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 3/25/2005
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B05-0959
|
| JOB ADDRESS: 11870 BARRYMORE DR , TX 75035 |
DESC:
3129 AC, 3736 SQ FT, SFR \ 2 STORY |
|
OWNER:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
CONTRACTOR:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
|
ISSUED DATE: 3/30/2005
APPLIED DATE:3/15/2005
EXPIRED DATE:9/29/2005
SITE APN:C2148765
STATUS:COMPLETED
|
|
APPLICANT:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 233454.69
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| DRY WALL 7/12/2005 CSW | $30.00 |
| UTILITY / ROW 09/07/2005 GAS | $30.00 |
| PRE POUR INSPECTION 4/12/2005 | $30.00 |
| FLATWORK 4/12/2005 GDS | $30.00 |
| FLATWORK 5/9/2005 GLC | $30.00 |
| SLAB 5/9/2005 GLC | $30.00 |
| 2NDS/FRAMING 6/16/2005 GLC | $30.00 |
| 2NDS/FRAMING 6/17/2005 GLC | $30.00 |
| 2NDS/FRAMING 6/23/2005 GLC | $30.00 |
| BRICK 7/6/2005 GLC | $30.00 |
| INSULATION 7/6/2005 GLC | $30.00 |
| RESIDENTIAL ELECTRIC FEE | $112.08 |
| MISCELLANOUS MECHANICAL FEES | $123.00 |
| MISCELLANEOUS PLUMBING FEES | $232.00 |
| BUILDING PERMIT FEE | $1,663.75 |
| FENCE FEE | $20.00 |
| INSULATION 7/1/2005 PDC | $30.00 |
| ELECTRICAL FINAL 8/25/2005 P | $30.00 |
| 1 INCH METER | $365.00 |
| LAWNSPRINKLERSYSTEM | $35.00 |
| PLUMBING FINAL 8/25/2005 | $30.00 |
| CO/BUILDING FINAL 9/21/2005 | $30.00 |
| Total Fees: | $3,000.83 |
|
|
|
| | ______ T-POLE |
| ______ WATER METER |
| ______ PLUMBING ROUGH-IN |
| ______ PRE POUR INSPECTION |
| ______ FLATWORK |
| ______ PRE POUR INSPECTION |
| ______ FLATWORK |
| ______ PRE POUR INSPECTION |
| ______ FLATWORK |
| ______ SLAB |
| ______ FLATWORK |
| ______ SLAB |
| ______ METER PAYMENT |
| ______ CAMERA |
| ______ PLUMBING TOP OUT |
| ______ 2NDS/FRAMING |
| ______ PLUMBING TOP OUT |
| ______ 2NDS/FRAMING |
| ______ 2NDS/FRAMING |
| ______ 2NDS/FRAMING |
| ______ INSULATION |
| ______ BRICK |
| ______ BRICK |
| ______ INSULATION |
| ______ BRICK |
| ______ INSULATION |
| ______ DRY WALL |
| ______ DRY WALL |
| ______ ELECTRICAL FINAL |
| ______ PLUMBING FINAL |
| ______ ELECTRICAL FINAL |
| ______ PLUMBING FINAL |
| ______ UTILITY / ROW |
| ______ UTILITY / ROW |
| ______ CO/BUILDING FINAL |
| ______ CO/BUILDING FINAL |
| ______ CO/BUILDING FINAL |