Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 3/24/2005 PERMIT SUB-TYPE: CNEW PERMIT NO: B05-0785
JOB ADDRESS:
7200 STONEBROOK PKWY
FRISCO, TX 75034
DESC:   84000 SQ FT, FRISCO POLICE HQTS-COMPLETE 11/29/2006
OWNER:
City of Frisco
6859 Main Street
Frisco TX 75034

CONTRACTOR:
LEE LEWIS CONSTRUCTION INC
17111 PRESTON RD, STE. 100
Dallas TX 75379
ISSUED DATE:
3/28/2005
APPLIED DATE:
3/8/2005
EXPIRED DATE:
9/24/2005
SITE APN:
C2665619
STATUS:
COMPLETED
APPLICANT:
LEE LEWIS CONSTRUCTION INC
17111 PRESTON RD, STE. 100
Dallas TX 75379
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
13675000
FEE SUMMARY
INSPECTION SUMMARY
WATER METER DEPOSIT$75.00
4 INCH TURB METER$1,130.00
WATER METER DEPOSIT$75.00
2 INCH TURB METER$615.00
PAVING 11/8/2005 JB$35.00
4 INCH COMP METER$1,270.00
MISCELLANEOUS ELECTRICAL FEES$0.00
MISCELLANOUS MECHANICAL FEES$0.00
MISCELLANEOUS PLUMBING FEES$0.00
COMMERCIAL BUILDING PERMIT FEE$0.00
Total Fees:$3,200.00
______  PIER
______  PIER
______  SLAB
______  SLAB
______  PLUMBING ROUGH-IN
______  PIER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB
______  PLUMBING ROUGH-IN
______  ELECTRICAL
______  PLUMBING ROUGH-IN
______  SLAB
______  ELECTRICAL
______  PAVING
______  ELECTRICAL
______  SLAB
______  PAVING
______  PAVING
______  PAVING
______  PAVING
______  PAVING
______  PLUMBING ROUGH-IN
______  BRICK
______  PLUMBING TOP OUT
______  BRICK/WALL TIES
______  BRICK
______  BRICK
______  BRICK
______  BRICK
______  BRICK
______  ELECTRICAL ROUGH IN
______  PLUMBING TOP OUT
______  MECHANICAL
______  FRAME
______  ELECTRICAL RELEASE
______  ELECTRICAL
______  ELECTRICAL
______  PLUMBING TOP OUT
______  ELECTRICAL
______  FRAME
______  ELECTRICAL
______  ELECTRICAL
______  FRAME
______  PLUMBING TOP OUT
______  ELECTRICAL
______  MECHANICAL
______  ELECTRICAL
______  ELECTRICAL
______  ELECTRICAL
______  MECHANICAL
______  MISC
______  PLUMBING ROUGH-IN
______  ELECTRICAL RELEASE
______  ELECTRICAL
______  ELECTRICAL
______  MISC
______  PAVING
______  ELECTRICAL
______  MECHANICAL
______  ELECTRICAL
______  GAS PRESSURE
______  MECHANICAL
______  COMM PLUMB TOP OUT
______  ELECTRICAL
______  MECHANICAL
______  GAS RELEASE
______  ELECTRICAL
______  ELECTRICAL
______  MECHANICAL
______  ELECTRICAL
______  MECHANICAL
______  ELECTRICAL
______  GAS RELEASE
______  ELECTRICAL
______  4 TURB METER
______  METER PAYMENT
______  PLUMBING FINAL
______  PLUMBING ROUGH-IN
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  MECHANICAL FINAL
______  MISCCO
______  PLUMBING FINAL
______  COMM PLUMB TOP OUT
______  ELECTRICAL
______  COMM PLUMB TOP OUT
______  SET 2 TURB METER
______  ELECTRICAL
______  CEILING
______  CEILING
______  4 PD METER
______  SET 2 TURB METER
Notes: