Phone: 972.292.5301
|
APPROVED DATE: 2/16/2005
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B05-0453
|
JOB ADDRESS: 4414 VENETO DR FRISCO, TX |
DESC:
4640 AC, 5650 SQ FT, SNEW / 2 STORY |
|
OWNER:
MANCHESTER CUSTOM HOMES X-2/05
P.O. BOX 262094 PLANO TX 75026
|
CONTRACTOR:
MANCHESTER CUSTOM HOMES X-2/05
P.O. BOX 262094 PLANO TX 75026
|
ISSUED DATE: 2/18/2005
APPLIED DATE:2/6/2005
EXPIRED DATE:8/17/2005
SITE APN:D234920
STATUS:COMPLETED
|
|
APPLICANT:
MANCHESTER CUSTOM HOMES X-2/05
P.O. BOX 262094 PLANO TX 75026
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 346190.4
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SLAB 3/22/2005 | $30.00 |
RESIDENTIAL ELECTRIC FEE | $169.50 |
MISCELLANOUS MECHANICAL FEES | $169.00 |
MISCELLANEOUS PLUMBING FEES | $284.00 |
BUILDING PERMIT FEE | $2,228.75 |
FENCE FEE | $20.00 |
1 INCH METER | $365.00 |
UTILITY / ROW 12/27/2005 GAS | $30.00 |
FLATWORK 10/4/2005 GDS | $30.00 |
2NDS/FRAMING 6/14/2005 | $30.00 |
PLUMBING TOP OUT 6/7/2005 GU | $30.00 |
PLUMBING TOP OUT 6/9/2005 GU | $30.00 |
INSULATION 7/5/2005 PDC | $30.00 |
PLUMBING FINAL 12/21/2005 PD | $30.00 |
PLUMBING FINAL 12/20/2005 | $30.00 |
PLUMBING FINAL 12/22/2005 | $30.00 |
DRY WALL 7/12/2005 TW | $30.00 |
BRICK 7/14/2005 TW | $30.00 |
BRICK 7/20/2005 TW | $30.00 |
Total Fees: | $3,626.25 |
|
|
| ______ WATER METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ SLAB |
______ CAMERA |
______ METER PAYMENT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ DRY WALL |
______ DRY WALL |
______ BRICK |
______ BRICK |
______ BRICK |
______ FLATWORK |
______ FLATWORK |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ UTILITY / ROW |
______ PLUMBING FINAL |
______ CO/BUILDING FINAL |
______ CAMERA |
______ ELECTRICAL FINAL |
______ PLUMBING ROUGH-IN |
______ FLATWORK |
______ 2NDS |
______ PLUMBING TOP OUT |
______ 2NDS |
______ PLUMBING TOP OUT |
______ INSULATION |
______ BRICK |
______ DRY WALL |
______ PLUMBING FINAL |
______ SLAB |
______ PLUMBING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|