BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 10/19/2004
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B04-3529
|
JOB ADDRESS: 2139 SANDY CREEK DR FRISCO, TX 75034 |
DESC:
3930 AC, 4654 SQ FT, SFR / 2 STORY |
|
OWNER:
LANDSTAR HOMES
5800 GRANITE PKWY PLANO TX 75024
|
CONTRACTOR:
LANDSTAR HOMES
5800 GRANITE PKWY PLANO TX 75024
|
ISSUED DATE: 10/25/2004
APPLIED DATE:9/29/2004
EXPIRED DATE:4/24/2005
SITE APN:D264908
STATUS:COMPLETED
|
|
APPLICANT:
LANDSTAR HOMES
5800 GRANITE PKWY PLANO TX 75024
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 293217.3
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
1 INCH METER | $365.00 |
PLUMBING TOP OUT 1/11/2005 C | $30.00 |
PLUMBING ROUGH-IN 10/29/2004 | $30.00 |
WATER USAGE ON NON FUNCTIONAL | $500.00 |
SLAB 11/15/2004 PDC | $30.00 |
ELECTRICAL FINAL 3/16/2005 T | $30.00 |
CO/BUILDING FINAL 3/28/2005 | $30.00 |
PLUMBING FINAL 3/21/2005 | $30.00 |
LAWNSPRINKLERSYSTEM | $35.00 |
CREDIT CARD CONVENIENCE FEE | $1.80 |
PLAN REVIEW FEE | $50.00 |
MISCELLANOUS MECHANICAL FEES | $136.00 |
MISCELLANEOUS PLUMBING FEES | $260.00 |
FENCE FEE | $20.00 |
BUILDING PERMIT FEE | $1,963.75 |
MISCELLANEOUS ELECTRICAL FEES | $139.62 |
2NDS/FRAMING 1/26/2005 | $30.00 |
2NDS/FRAMING 1/28/2005 | $30.00 |
Total Fees: | $3,711.17 |
|
|
| ______ T-POLE |
______ PLUMBING ROUGH-IN |
______ WATER METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ BRICK/WALL TIES |
______ DRY WALL |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|