BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 10/4/2004
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B04-3308
|
JOB ADDRESS: 12133 FLYNT DR FRISCO, TX 75035 |
DESC:
3434 AC, 4290 SQ FT, SFR / 2 STORY |
|
OWNER:
DARLING HOMES
2500 LEGACY #100 FRISCO TX 75034
|
CONTRACTOR:
DARLING HOMES
2500 LEGACY #100 FRISCO TX 75034
|
ISSUED DATE: 10/7/2004
APPLIED DATE:9/8/2004
EXPIRED DATE:4/6/2005
SITE APN:C2537115
STATUS:COMPLETED
|
|
APPLICANT:
DARLING HOMES
2500 LEGACY #100 FRISCO TX 75034
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 256210.74
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
1 INCH METER | $365.00 |
UTILITY / ROW 2/11/2005 GAS | $30.00 |
2NDS/FRAMING 11/16/2004 GDS | $30.00 |
BRICK 12/9/2004 GDS | $30.00 |
T-POLE 10/7/2004 GLQ | $30.00 |
PLUMBING TOP OUT 11/9/2004 G | $30.00 |
PLUMBING TOP OUT 11/16/2004 | $30.00 |
PLUMBING TOP OUT 11/22/2004 | $30.00 |
RESIDENTIAL ELECTRIC FEE | $0.00 |
MISCELLANOUS MECHANICAL FEES | $0.00 |
MISCELLANEOUS PLUMBING FEES | $0.00 |
BUILDING PERMIT FEE | $1,778.75 |
FENCE FEE | $20.00 |
SLAB 10/14/2004 JM | $30.00 |
PLUMBING FINAL 1/12/2005 | $30.00 |
BUILDING FINAL 2/18/2005 MC | $30.00 |
LAWNSPRINKLERSYSTEM | $35.00 |
CREDIT CARD CONVENIENCE FEE | $3.20 |
Total Fees: | $2,501.95 |
|
|
| ______ T-POLE |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ WATER METER |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ INSULATION |
______ DRY WALL |
______ BRICK |
______ BRICK |
______ FLATWORK |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ BUILDING FINAL |
______ BUILDING FINAL |
______ METER PAYMENT |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|