BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 9/16/2004
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B04-3115
|
JOB ADDRESS: 5755 SWEENEY TRL , TX 75034 |
DESC:
4905 AC, 5694 SQ FT, SFR / 2 STORY |
|
OWNER:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
CONTRACTOR:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
ISSUED DATE: 9/23/2004
APPLIED DATE:8/27/2004
EXPIRED DATE:3/22/2005
SITE APN:C2557540
STATUS:COMPLETED
|
|
APPLICANT:
HUNTINGTON HOMES
12850 HILLCREST RD #200 DALLAS TX 75230
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 365962.05
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLUMBING ROUGH-IN 12/16/2004 | $30.00 |
1 INCH METER | $365.00 |
ELECTRICAL FINA 3/23/2005 | $30.00 |
PLAN REVIEW FEE | $50.00 |
RESIDENTIAL ELECTRIC FEE | $170.82 |
MISCELLANOUS MECHANICAL FEES | $162.50 |
MISCELLANEOUS PLUMBING FEES | $274.00 |
BUILDING PERMIT FEE | $2,323.75 |
FENCE FEE | $20.00 |
PLUMBING FINAL 4/1/2005 PDC | $30.00 |
LAWNSPRINKLERSYSTEM | $35.00 |
PLUMBING FINAL 3/30/2005 TP | $30.00 |
PLUMBING TOP OU 1/26/2005 | $30.00 |
Total Fees: | $3,551.07 |
|
|
| ______ T-POLE |
______ WATER METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ FLATWORK |
______ SLAB |
______ FLATWORK |
______ CAMERA |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ INSULATION |
______ INSULATION |
______ INSULATION |
______ BRICK |
______ DRY WALL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
______ METER PAYMENT |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|