|
BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 7/17/2004
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B04-2402
|
JOB ADDRESS: 10657 LINE BERRY LN , TX 75035 |
DESC:
2401 AC, 2897 SQ FT, SFR / 1 STORY |
|
OWNER:
FIRST TEXAS HOMES
2221 E LAMAR #960 ARLINGTON TX 76006
|
CONTRACTOR:
FIRST TEXAS HOMES
2221 E LAMAR #960 ARLINGTON TX 76006
|
ISSUED DATE: 7/20/2004
APPLIED DATE:6/30/2004
EXPIRED DATE:1/19/2005
SITE APN:C2537908
STATUS:COMPLETED
|
|
APPLICANT:
FIRST TEXAS HOMES
2221 E LAMAR #960 ARLINGTON TX 76006
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 179138.61
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
RESIDENTIAL ELECTRIC FEE | $86.91 |
MISCELLANOUS MECHANICAL FEES | $96.50 |
MISCELLANEOUS PLUMBING FEES | $188.00 |
BUILDING PERMIT FEE | $1,393.75 |
FENCE FEE | $20.00 |
1 INCH METER | $365.00 |
ELECTRICAL FINAL 10/5/2004 G | $30.00 |
SLAB 8/5/2004 JM | $30.00 |
PLUMBING FINAL 9/30/2004 TRC | $30.00 |
Total Fees: | $2,275.16 |
|
|
| ______ WATER METER |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ SLAB |
______ CAMERA |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ FLATWORK |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS |
______ INSULATION |
______ DRY WALL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|