BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 6/9/2004
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B04-1755
|
JOB ADDRESS: 11700 CHAUCER DR FRISCO, TX 75035 |
DESC:
2863 AC, 3465 SQ FT, SFR \ 2 STORY |
|
OWNER:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
CONTRACTOR:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
ISSUED DATE: 6/16/2004
APPLIED DATE:5/17/2004
EXPIRED DATE:12/15/2004
SITE APN:C2148719
STATUS:COMPLETED
|
|
APPLICANT:
GRAND HOMES
8350 N CENTRAL EXPRSWY, SUITE DALLAS TX 75206
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 213608.43
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
RESIDENTIAL ELECTRIC FEE | $103.95 |
MISCELLANOUS MECHANICAL FEES | $96.50 |
MISCELLANEOUS PLUMBING FEES | $195.00 |
BUILDING PERMIT FEE | $1,563.75 |
FENCE FEE | $20.00 |
WATER METER 06/18/2004 JR | $30.00 |
WATER METER 06/28/2004 JR | $30.00 |
UTILITY / ROW 10/13/2004 GAS | $30.00 |
1 INCH METER | $365.00 |
PLUMBING FINAL 9/28/2004 MBW | $30.00 |
T-POLE 6/18/2004 TG | $30.00 |
SLAB 6/29/2004 TG | $30.00 |
SLAB 7/1/2004 TG | $30.00 |
SLAB 7/2/2004 TG | $30.00 |
SLAB 7/7/2004 TG | $30.00 |
PLUMBING TOP OUT 8/9/2004 TG | $30.00 |
2NDS 8/12/2004 WKT | $30.00 |
2NDS 8/13/2004 WKT | $30.00 |
Total Fees: | $2,739.20 |
|
|
| ______ T-POLE |
______ WATER METER |
______ T-POLE |
______ T-POLE |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ T-POLE |
______ WATER METER |
______ SLAB |
______ SLAB |
______ FLATWORK |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ FLATWORK |
______ FLATWORK |
______ SLAB |
______ SLAB |
______ CAMERA |
______ FLATWORK |
______ WATER METER |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS |
______ 2NDS |
______ 2NDS |
______ 2NDS |
______ INSULATION |
______ DRY WALL |
______ BRICK |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ FINAL BUILDING APPRO |
______ CO/BUILDING FINAL |
|
|
|