APPROVED DATE: 12/23/2003
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B03-3354
|
JOB ADDRESS: 3245 MAIN ST FRISCO, TX 75034 |
DESC:
34925 SQ FT, CNEW / Main St Village-BLDG C |
|
OWNER:
Cencor Realty Services
3102 Maple Ave. Suite 500 Dallas TX 75201
|
CONTRACTOR:
KIBLER CONSTRUCTION
DALLAS
|
ISSUED DATE: 3/8/2004
APPLIED DATE:12/1/2003
EXPIRED DATE:9/7/2004
SITE APN:D271919
STATUS:COMPLETED
|
|
APPLICANT:
MICHAEL TWITCHELL, LP
3624 OAK LAWN AVE DALLAS TX 75219
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 1325753
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
2 INCH PD METER | $565.00 |
MISCELLANEOUS ELECTRICAL FEES | $762.50 |
MISCELLANEOUS PLUMBING FEES | $90.00 |
COMMERCIAL BUILDING PERMIT FEE | $3,981.39 |
MISCELLANOUS MECHANICAL FEES | $38.30 |
Total Fees: | $5,437.19 |
|
|
| ______ SLAB |
______ SLAB |
______ PRE POUR INSPECTION |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ BRICK/WALL TIES |
______ BRICK/WALL TIES |
______ PLUMBING ROUGH-IN |
______ FLATWORK |
______ SLAB |
______ PIER |
______ PIER |
______ WATER METER |
______ DUMPSTER |
______ FRAME |
______ ELECTRICAL |
______ ELECTRICAL |
______ ELECTRICAL RELEASE |
______ SEWER |
______ ELECTRICAL |
______ FRAME |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ CO |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|