BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 11/24/2003
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B03-3245
|
JOB ADDRESS: 5345 MONTEREY DR FRISCO, TX 75034 |
DESC:
11666 AC, 14909 SQ FT, SFR / 2 STORY |
|
OWNER:
Steve Roberts Custom Builders
5301 Village Creek Dr., Suite Plano TX 75093
|
CONTRACTOR:
Steve Roberts Custom Builders
5301 Village Creek Dr., Suite Plano TX 75093
|
ISSUED DATE: 11/26/2003
APPLIED DATE:11/14/2003
EXPIRED DATE:6/1/2006
SITE APN:C2142990
STATUS:COMPLETED
|
|
APPLICANT:
Steve Roberts Custom Builders
5301 Village Creek Dr., Suite Plano TX 75093
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 870400.26
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
LAWNSPRINKLERSYSTEM | $35.00 |
PLUMBING TOP OUT 11/5/2004 C | $30.00 |
CONVENIENCE FEE | $0.90 |
CONVENIENCE FEE | $0.90 |
1 INCH METER | $365.00 |
2NDS/FRAMING 11/23/2004 GLQ | $30.00 |
T-POLE 12/2/2003 GU | $30.00 |
UTILITY / ROW 3/30/2007 KB | $30.00 |
PLUMBING TOP OUT 10/26/2004 | $30.00 |
2NDS/FRAMING 11/24/2004 MC | $30.00 |
PLUMBING FINAL 11/17/06 | $30.00 |
SLAB 3/18/2004 RM | $30.00 |
PLUMBING ROUGH-IN 2/23/2004 | $30.00 |
MISCELLANEOUS PLUMBING FEES | $443.00 |
BUILDING PERMIT FEE | $4,996.00 |
RESIDENTIAL ELECTRIC FEE | $447.27 |
MISCELLANOUS MECHANICAL FEES | $261.00 |
FENCE FEE | $20.00 |
Total Fees: | $6,839.07 |
|
|
| ______ PIER |
______ T-POLE |
______ PIER |
______ T-POLE |
______ FOOTINGS |
______ WATER METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ SLAB |
______ CAMERA |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ 2NDS/FRAMING |
______ INSULATION |
______ DRY WALL |
______ BRICK/WALL TIES |
______ METER PAYMENT |
______ FLATWORK |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ UTILITY / ROW |
______ CO/BUILDING FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|