BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 11/18/2003
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B03-2402
|
JOB ADDRESS: 7600 JOHN Q HAMMONS FRISCO, TX 75034 |
DESC:
309788 SQFT CNEW / EMBASSY SUITES HOTEL(HOTEL PHASE) |
|
OWNER:
EMBASSY SUITES
300 SOUTH JEFFERSON SUITE #505 SPRINGFIELD MO 65806
|
CONTRACTOR:
CDI CONTRACTORS, LLC
PO BOX 686 LITTLE ROCK AR 72203
|
ISSUED DATE: 11/26/2003
APPLIED DATE:8/14/2003
EXPIRED DATE:5/25/2003
SITE APN:C2545237
STATUS:COMPLETED
|
|
APPLICANT:
BUTLER ROSENBURY & PARTNERS
300 SOUTH JEFFERSON SUITE #505 SPRINGFIELD MO 65806
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 31000000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
MISCELLANEOUS BUILDING PERMIT | $460.00 |
1 INCH WATER TAP | $440.00 |
1 INCH METER | $365.00 |
6 INCH COMP METER | $3,775.00 |
LAWNSPRINKLERSYSTEM | $35.00 |
PLUMBING ROUGH-IN 3/10/2004 | $35.00 |
PLUMBING TOP OUT 7/26/2004 T | $35.00 |
MISCELLANEOUS BUILDING PERMIT | $12,000.00 |
MISCELLANEOUS PLUMBING FEES | $11,897.00 |
COMMERCIAL BUILDING PERMIT FEE | $60,067.14 |
MISCELLANOUS MECHANICAL FEES | $2,731.15 |
MISCELLANEOUS ELECTRICAL FEES | $12,683.68 |
REVISION / ADDENDUM FEE | $1,450.00 |
MISCELLANEOUS ELECTRICAL FEES | $153.12 |
MISCELLANOUS MECHANICAL FEES | $400.40 |
MISCELLANEOUS PLUMBING FEES | $286.00 |
1.5 INCH WATER TAP | $460.00 |
MISCELLANEOUS BUILDING PERMIT | $650.00 |
MISCELLANEOUS ELECTRICAL FEES | $200.00 |
MISCELLANOUS MECHANICAL FEES | $108.70 |
MISCELLANEOUS PLUMBING FEES | $115.00 |
Total Fees: | $108,347.19 |
|
|
| ______ SLAB |
______ PIER |
______ SLAB |
______ SLAB |
______ T-POLE |
______ T-POLE |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ PLUMBING ROUGH-IN |
______ ELECTRICAL ROUGH IN |
______ FRAME |
______ PLUMBING ROUGH-IN |
______ SLAB |
______ BUILDING INSPECTION |
______ ELECTRICAL ROUGH IN |
______ BUILDING FINAL |
______ BUILDING FINAL |
______ FRAME |
______ |
______ SEWER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ BUILDING FINAL |
______ FRAME |
______ PLUMBING ROUGH-IN |
______ SEWER |
______ MECHANICAL |
______ CO |
______ FRAME |
______ 2NDS |
______ PLUMBING ROUGH-IN |
______ MECHANICAL |
______ FRAME |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ ELECTRICAL |
______ PLUMBING TOP OUT |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ FRAME |
______ PLUMBING ROUGH-IN |
______ PLUMBING TOP OUT |
______ PLUMBING TOP OUT |
______ FRAME |
______ PLUMBING TOP OUT |
______ FRAME |
______ PLUMBING TOP OUT |
______ FRAME |
______ PLUMBING TOP OUT |
______ FRAME |
______ FRAME |
______ FRAME |
______ ELEC WALL |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ 2NDS/FRAMING |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ FRAME |
______ MECHANICAL |
______ FRAME |
______ PLUMBING ROUGH-IN |
______ FRAME |
______ MECHANICAL |
______ MECHANICAL |
______ ELECTRICAL |
______ FRAME |
______ ELEC WALL |
______ ELECTRICAL RELEASE |
______ ELECTRICAL FINAL |
______ PLUMBING TOP OUT |
______ 2NDS/FRAMING |
______ ELECTRICAL |
______ GAS PRESSURE |
______ PAVING |
______ GAS PRESSURE |
______ PAVING |
______ FRAME |
______ PAVING |
______ GAS PRESSURE |
______ PAVING |
______ FRAME |
______ PAVING |
______ PAVING |
______ GAS RELEASE |
______ FRAME |
______ CEILING |
______ PAVING |
______ ELECTRICAL |
______ FRAME |
______ PRE PLASTER |
______ CEILING |
______ ELECTRICAL |
______ CEILING |
______ MECHANICAL |
______ ELECTRICAL |
______ PAVING |
______ PAVING |
______ PLUMBING TOP OUT |
______ CEILING |
______ MECHANICAL |
______ CEILING |
______ FRAME |
______ ELECTRICAL |
______ CEILING |
______ HEALTH FINAL |
______ PIER |
______ CEILING |
______ CEILING |
______ WATER METER |
______ ELECTRICAL FINAL |
______ ELECTRICAL FINAL |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ CO/BUILDING FINAL |
______ PLUMBING FINAL |
______ WATER METER |
______ PLUMBING FINAL |
______ ELECTRICAL FINAL |
______ METER PAYMENT |
|
|
|