APPROVED DATE: 5/22/2003 PERMIT SUB-TYPE: CNEW PERMIT NO: B03-1437
JOB ADDRESS:
7600 STONEBROOK PKWY
FRISCO, TX 75034
DESC:   4474 SQ FT, CNEW / DR CHARLIE MORGAN DDS
OWNER:
DR CHARLIE MORGAN DDS


CONTRACTOR:
JERRY HUFFMAN CB X-10/03
1320 VILLAGE CREEK, STE 200
PLANO TX 75093
ISSUED DATE:
5/23/2003
APPLIED DATE:
5/7/2003
EXPIRED DATE:
11/19/2003
SITE APN:
C957441
STATUS:
COMPLETED
APPLICANT:
JERRY HUFFMAN CB X-10/03
1320 VILLAGE CREEK, STE 200
PLANO TX 75093
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
315000
FEE SUMMARY
INSPECTION SUMMARY
FRAME 7/1/2003 JB$35.00
5/8 INCH METER$315.00
LAWNSPRINKLERSYSTEM$35.00
LAWNSPRINKLERSYSTEM$35.00
CEILING 8/27/2003 JB$35.00
FRAME 8/21/2003 JB$35.00
DUCT 8/19/2003 JB$35.00
DUCT ROUGH 8/12/2003 JB$35.00
MISCELLANEOUS PLUMBING FEES$237.00
MISCELLANOUS MECHANICAL FEES$150.00
MISCELLANEOUS ELECTRICAL FEES$313.18
COMMERCIAL BUILDING PERMIT FEE$1,241.25
Total Fees:$2,501.43
______  PLUMBING ROUGH-IN
______  SLAB
______  CAMERA
______  FRAME
______  FRAME
______  FRAME
______  PLUMBING TOP OUT
______  ELEC WALL
______  DUCT ROUGH
______  DUCT
______  DUCT
______  CEILING
______  FRAME
______  CEILING
______  CEILING
______  CEILING
______  CEILING
______  ELECTRICAL RELEASE
______  INSULATION
______  FRAME
______  DRY WALL
______  DRY WALL
______  WATER METER
______  ELECTRICAL RELEASE
______  GAS AIR TEST
______  CEILING
______  GAS PRESSURE
______  PLUMBING FINAL
______  ELECTRICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)