APPROVED DATE: 5/13/2002 PERMIT SUB-TYPE: CNEW PERMIT NO: B02-1129
JOB ADDRESS:
8119 ROBERTSON DR
FRISCO, TX
DESC:   960 SQ FT AMENITY CENTER / HERITAGE VILLAGE
OWNER:
DALWESTERN FRISCO
17915 WIND FLOWER STE 104
DALLAS TX 75252

CONTRACTOR:
DOYLE NIX AMENITIES LP
P O BOX 116636
CARROLLTON TX 75011
ISSUED DATE:
5/13/2002
APPLIED DATE:
4/22/2002
EXPIRED DATE:
11/9/2002
SITE APN:
D237884
STATUS:
COMPLETED
APPLICANT:
DOYLE NIX AMENITIES LP
P O BOX 116636
CARROLLTON TX 75011
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
52627.2
FEE SUMMARY
INSPECTION SUMMARY
COMMERCIAL BUILDING PERMIT FEE$398.85
ELECTRICAL FINAL 9/17/2002 R$30.00
LAWNSPRINKLERSYSTEM$35.00
PLUMBING FEE$133.00
PLUMBING ROUGH-IN 5/23/2002$30.00
SLAB 6/3/2002 TC$30.00
SLAB 6/4/2002 TG$30.00
COMMERCIAL ELECTRIC FEE$38.40
Total Fees:$725.25
______  FLATWORK
______  FLATWORK
______  T-POLE
______  T-POLE
______  FLATWORK
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB
______  SLAB
______  SLAB
______  FLATWORK
______  BRICK/WALL TIES
______  PLUMBING TOP OUT
______  2NDS
______  INSULATION
______  ELECTRICAL ROUGH IN
______  DRY WALL
______  FLATWORK
______  ELECTRICAL RELEASE
______  ELECTRICAL FINAL
______  ELECTRICAL FINAL
______  CO
______  CO
______  CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)