Permit Info
Short Description:
19957 SF, FRISCO POLICE DEPARTMENT AUXILLARY BUILDING
Expiration Date:
7/14/2025
Parcel Info
City/State/Zip:
FRISCO, TX, 75034
Subdivision:
NWC STONEBROOK & PARKWOOD (CFR)
|
APPLICANT | Gunjali Mirajkar | (214)647-6431 | gmirajkar@pgal.com | 14135 Midway rd | Addison, TX 75001 |
OWNER | FRISCO CITY OF | ()- | | | FRISCO, TX 75034-3253 |
CONTRACTOR | BYRNE CONSTRUCTION | (817)335-3394 | ltieh@tsbyrne.com | 551 EAST BERRY | FT WORTH, TX 76110 |
ELECT. CTR. | TITAN ELECTRIC | (469)858-0700 | trb@titanelectric-tx.com | 1250 POST AND PADDOCK STE 100 | GRAND PRAIRE, TX 75050 |
MECH. CTR. | AIR 817, INC. (MECH) | (817)381-5002 | MIKE@AIR817.COM | 5808 DENTON HIGHWAY | HALTOM CITY, TX 76148 |
PLUM. CTR. | PARAMOUNT PLUMBING LLC | (817)900-2030 | PHILIPB@PARAMOUNT-PLUMBING.NET | 7415 Whitehall St., Ste 109 | Richland Hills, TX 76118 |
OTHER | MAVERICK UTILITY CONSTRUCTION (PLUMB) | (817)658-9592 | MNEWBERN@MAVUTILITY.COM | 1001 W EULESS BLVD | EULESS, TX 76040 |
|
PERCENT CREDIT CARD FEE |
$0.70
|
8/31/2023
|
PERCENT CREDIT CARD FEE |
$24.20
|
2/19/2024
|
2 INCH T-10 METER |
$1,210.00
|
2/19/2024
|
WATER METER DEPOSIT COMMERCIAL |
$0.00
|
|
PLUMBING ROUGH-IN 07/27/2023 MLM |
$35.00
|
8/31/2023
|
AUTO PROCESSING FEE |
$6.00
|
10/27/2022
|
COMMERCIAL FEE |
$0.00
|
|
COMMERCIAL BUILDING PERMIT FEE |
$0.00
|
|
COMMERCIAL MECHANICAL FEE |
$0.00
|
|
COMMERCIAL NEW APPLICATION FEE |
$300.00
|
10/27/2022
|
COMMERCIAL PLUMBING FEE |
$0.00
|
|
SEWER IMPACT FEE |
$0.00
|
|
THOROUGHFARE IMPACT FEE |
$0.00
|
|
WATER IMPACT FEE |
$0.00
|
|
Total Fees |
Charged: $1,575.90
Balance Due: $0.00
|
|
COMM CO | |
2/14/2025
| | | |
More Info
|
COMM CO | TEMP CO |
1/15/2025
| | 1/15/2025 | |
More Info
|
COMM CO | TEMP CO |
12/16/2024
| | 12/16/2024 | |
More Info
|
COMM CO | TEMP CO |
9/16/2024
| | 9/16/2024 | |
More Info
|
COMM CO | TEMP CO |
8/16/2024
| | 8/16/2024 | |
More Info
|
COMM CO | TEMP CO |
7/17/2024
| | 7/17/2024 | |
More Info
|
COMM CO | TEMP CO |
6/17/2024
| | 6/17/2024 | |
More Info
|
COMM CO | TEMP CO |
6/5/2024
| | 6/5/2024 | |
More Info
|
COMM CO | TEMP CO |
5/6/2024
| | 5/6/2024 | |
More Info
|
PLUMBING FINAL | CANCELLED |
4/26/2024
| | 4/26/2024 | |
More Info
|
COMM CO | TEMP CO |
4/5/2024
| | 4/5/2024 | |
More Info
|
FIRE FINAL | APPROVED |
4/3/2024
| 8:00 AM | 4/3/2024 | |
More Info
|
COMM CO | CANCELLED |
4/3/2024
| | 4/3/2024 | |
More Info
|
ELECT FINAL COMM | APPROVED |
3/22/2024
| | 3/22/2024 | |
More Info
|
MECHANICAL FINAL | APPROVED |
3/22/2024
| | 3/22/2024 | |
More Info
|
PLUMBING FINAL | APPROVED |
3/22/2024
| | 3/22/2024 | |
More Info
|
FIRE FINAL | PARTIAL APPROVAL |
3/20/2024
| | 3/19/2024 | |
More Info
|
PLUMBING FINAL | COMM FAILED |
3/8/2024
| | 3/8/2024 | |
More Info
|
MECHANICAL FINAL | COMM FAILED |
3/8/2024
| | 3/8/2024 | |
More Info
|
SET 2 T-10 METER | APPROVED |
2/22/2024
| 9:00 AM | 2/22/2024 | |
More Info
|
METER PAYMENT | APPROVED |
2/19/2024
| | 2/19/2024 | |
More Info
|
CEILING | APPROVED |
2/15/2024
| | 2/15/2024 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
2/14/2024
| | 2/14/2024 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
2/13/2024
| | 2/13/2024 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
2/9/2024
| | 2/9/2024 | |
More Info
|
PLUMBING TOP OUT | APPROVED |
1/9/2024
| | 1/9/2024 | |
More Info
|
FRAME COMM | APPROVED |
12/12/2023
| | 12/12/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
12/12/2023
| | 12/12/2023 | |
More Info
|
INSULATION COMM | APPROVED |
12/12/2023
| | 12/12/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
12/12/2023
| | 12/12/2023 | |
More Info
|
FIRE RATED WALL COMM | APPROVED |
12/12/2023
| | 12/12/2023 | |
More Info
|
BRICKWALL TIE COMM | PARTIAL APPROVAL |
11/28/2023
| | 11/28/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
11/14/2023
| | 11/14/2023 | |
More Info
|
PIER COMM | APPROVED |
10/6/2023
| | 10/6/2023 | |
More Info
|
PIER COMM | CANCELLED |
10/5/2023
| | 10/5/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
9/13/2023
| | 9/13/2023 | |
More Info
|
FIRELANE INSPECTION | APPROVED |
9/6/2023
| 2:30 PM | 9/7/2023 | |
More Info
|
INSPECTION ASSIST | COMPLETED |
9/6/2023
| | 9/7/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/24/2023
| | 8/24/2023 | |
More Info
|
CEILING | CANCELLED |
8/21/2023
| | 8/21/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/21/2023
| | 8/21/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/18/2023
| | 8/18/2023 | |
More Info
|
SLAB COMM | APPROVED |
8/15/2023
| | 8/15/2023 | |
More Info
|
SLAB COMM | CANCELLED |
8/9/2023
| | 8/9/2023 | |
More Info
|
PAVING | CANCELLED |
7/28/2023
| | 7/28/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/28/2023
| | 7/28/2023 | |
More Info
|
FOOTINGS COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
7/27/2023
| | 7/27/2023 | |
More Info
|
PIER COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
7/26/2023
| | 7/26/2023 | |
More Info
|
ELECT ROUGH COMM | CANCELLED |
7/25/2023
| | 7/25/2023 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
7/24/2023
| | 7/24/2023 | |
More Info
|
PLUMBING ROUGH-IN | PARTIAL APPROVAL |
7/17/2023
| | 7/17/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/13/2023
| | 7/13/2023 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
7/12/2023
| | 7/12/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/12/2023
| | 7/12/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
5/15/2023
| | 5/15/2023 | |
More Info
|
T-POLE COMM | APPROVED |
4/27/2023
| | 4/27/2023 | |
More Info
|
MEETING | COMPLETED |
4/19/2023
| 1:30 PM | 4/21/2023 | |
More Info
|
There are currently no reviews on this record.