Permit Info
Short Description:
8698 SF, SHAWNEE TRAIL CHURCH OF CHRIST
Expiration Date:
10/8/2025
Parcel Info
City/State/Zip:
FRISCO, TX, 75033
Subdivision:
SHAWNEE TRAIL CHURCH OF CHRIST (CFR)
|
APPLICANT | Dirk Dalhausser | (972)800-3662 | ddalhausser@goffcompanies.com | 2221 Lakeside Boulevard | Richardson, TX 75082 |
OWNER | TRAIL CHURCH OF CHRIST INC SHA | (972)979-5924 | jathan.floren@haskell.com | 10633 JOHN W ELLIOTT DR STE 3 | FRISCO, TX 75033-2010 |
CONTRACTOR | Goff Construction Services, LLC | (214)716-5100 | reldridge@goffcompanies.com | 2221 Lakeside Blvd | Richardson, TX 75082 |
ELECT. CTR. | MECHANICAL PARTNERS (ELEC) | (214)343-1105 | permit@mechanicalpartners.com | 300 Crepe Myrtle Lane | Murphy, TX 75094 |
MECH. CTR. | MECHANICAL PARTNERS | (214)343-1105 | permit@mechanicalpartners.com | 3541 W. Miller Rd. | Garland, TX 75041 |
PLUM. CTR. | MECHANICAL PARTNERS (PLBG) | (214)343-1105 | permit@mechanicalpartners.com | 3541 W Miller Rd | Garland, TX 75041 |
|
SET 2 T-10 METER 07/25/2024 BCB |
$100.00
|
|
SET 2 T-10 METER 07/24/2024 CDR |
$100.00
|
|
FOOTINGS COMM 09/03/2024 DW2 |
$30.00
|
|
AUTO PROCESSING FEE |
$6.00
|
11/14/2023
|
COMMERCIAL FEE |
$377.92
|
5/13/2024
|
COMMERCIAL BUILDING PERMIT FEE |
$13,518.84
|
5/13/2024
|
COMMERCIAL MECHANICAL FEE |
$464.90
|
5/13/2024
|
COMMERCIAL NEW APPLICATION FEE |
$300.00
|
11/14/2023
|
COMMERCIAL PLUMBING FEE |
$812.82
|
5/13/2024
|
SEWER IMPACT FEE |
$10,714.00
|
5/13/2024
|
THOROUGHFARE IMPACT FEE |
$12,690.00
|
5/13/2024
|
WATER IMPACT FEE |
$12,718.00
|
5/13/2024
|
2 INCH T-10 METER |
$1,210.00
|
7/22/2024
|
WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
7/22/2024
|
Total Fees |
Charged: $54,142.48
Balance Due: $230.00
|
|
LANDSCAPE | |
4/17/2025
| | | |
More Info
|
COMM CO | COMM FAILED |
4/17/2025
| | 4/17/2025 | |
More Info
|
FIRE FINAL | APPROVED |
4/11/2025
| 7:45 AM | 4/11/2025 | |
More Info
|
MECHANICAL FINAL | APPROVED |
4/9/2025
| | 4/9/2025 | |
More Info
|
PLUMBING FINAL | APPROVED |
4/8/2025
| | 4/8/2025 | |
More Info
|
ELECT FINAL COMM | APPROVED |
4/8/2025
| | 4/8/2025 | |
More Info
|
ELECT ROUGH COMM | CANCELLED |
4/4/2025
| | 4/4/2025 | |
More Info
|
PLUMBING TOP OUT | APPROVED |
4/4/2025
| | 4/4/2025 | |
More Info
|
MEETING | COMPLETED |
4/3/2025
| 8:00 AM | 4/3/2025 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
4/1/2025
| | 4/1/2025 | |
More Info
|
CEILING | APPROVED |
3/28/2025
| | 3/28/2025 | |
More Info
|
FIRE FINAL | FIRE FAILED |
3/25/2025
| 2:00 PM | 3/25/2025 | |
More Info
|
FLATWORK COMM | APPROVED |
3/11/2025
| | 3/11/2025 | |
More Info
|
MEETING | COMPLETED |
3/3/2025
| 10:30 AM | 3/3/2025 | |
More Info
|
CEILING | COMM FAILED |
2/24/2025
| | 2/24/2025 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
2/24/2025
| | 2/24/2025 | |
More Info
|
PLUMBING FINAL | PARTIAL APPROVAL |
2/24/2025
| | 2/24/2025 | |
More Info
|
MECHANICAL FINAL | PARTIAL APPROVAL |
2/24/2025
| | 2/24/2025 | |
More Info
|
FLATWORK COMM | APPROVED |
2/13/2025
| | 2/13/2025 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
2/4/2025
| | 2/4/2025 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
1/29/2025
| | 1/29/2025 | |
More Info
|
ELECT RELEASE COMM | COMM FAILED |
1/28/2025
| | 1/28/2025 | |
More Info
|
ELECT RELEASE COMM | COMM FAILED |
1/27/2025
| | 1/27/2025 | |
More Info
|
SET 2 T-10 METER | APPROVED |
1/24/2025
| 7:30 AM | 1/24/2025 | |
More Info
|
CEILING | APPROVED |
1/16/2025
| | 1/16/2025 | |
More Info
|
GAS PRESSURE | APPROVED |
1/15/2025
| | 1/14/2025 | |
More Info
|
GAS RELEASE | APPROVED |
1/14/2025
| | 1/14/2025 | |
More Info
|
DRYWALL COMM | APPROVED |
1/8/2025
| | 1/8/2025 | |
More Info
|
FLATWORK COMM | APPROVED |
1/2/2025
| | 1/2/2025 | |
More Info
|
GAS RELEASE | CANCELLED |
12/31/2024
| | 12/31/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
12/23/2024
| | 12/23/2024 | |
More Info
|
FLATWORK COMM | APPROVED |
12/13/2024
| | 12/13/2024 | |
More Info
|
INSULATION COMM | APPROVED |
12/11/2024
| | 12/11/2024 | |
More Info
|
INSULATION COMM | COMM FAILED |
12/6/2024
| | 12/6/2024 | |
More Info
|
LATH COMM | APPROVED |
12/6/2024
| | 12/6/2024 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
11/27/2024
| | 11/27/2024 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
11/25/2024
| | 11/25/2024 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
11/25/2024
| | 11/25/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
11/25/2024
| | 11/25/2024 | |
More Info
|
FRAME COMM | APPROVED |
11/25/2024
| | 11/25/2024 | |
More Info
|
MECHANICAL ROUGH | COMM FAILED |
11/20/2024
| | 11/20/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
11/11/2024
| | 11/11/2024 | |
More Info
|
ELECT ROUGH COMM | CANCELLED |
11/8/2024
| | 11/8/2024 | |
More Info
|
MECHANICAL ROUGH | COMM FAILED |
11/5/2024
| | 11/5/2024 | |
More Info
|
FRAME COMM | APPROVED |
11/1/2024
| | 11/1/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
SLAB COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/12/2024
| | 9/12/2024 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/3/2024
| | 9/3/2024 | |
More Info
|
FOOTINGS COMM | RES FAILED |
9/3/2024
| | 9/3/2024 | |
More Info
|
SLAB COMM | CANCELLED |
9/3/2024
| | 9/3/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
FOOTINGS COMM | APPROVED |
8/23/2024
| | 8/23/2024 | |
More Info
|
FIRELANE INSPECTION | APPROVED |
7/30/2024
| 9:00 AM | 7/30/2024 | |
More Info
|
SET 2 T-10 METER | WM NOT READY |
7/25/2024
| 7:15 AM | 7/25/2024 | |
More Info
|
SET 2 T-10 METER | WM NOT READY |
7/24/2024
| 9:15 AM | 7/24/2024 | |
More Info
|
METER PAYMENT | APPROVED |
7/22/2024
| | 7/22/2024 | |
More Info
|
FOOTINGS COMM | APPROVED |
7/18/2024
| | 7/18/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/18/2024
| | 7/18/2024 | |
More Info
|
PAVING | APPROVED |
6/28/2024
| | 6/28/2024 | |
More Info
|
T-POLE COMM | APPROVED |
5/20/2024
| | 5/20/2024 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
5/20/2024
| | 5/20/2024 | |
More Info
|
There are currently no reviews on this record.