Permit Info
Short Description:
690973 SF, BRINKMANN RANCH PHASE 1
Approved Date:
12/21/2022
Expiration Date:
2/25/2026
Notes:
8/26/2022 11:28:56 AM
Energy Code is under the 2018 IECC Residential for the residential portion and must be inspected and tested as such.
Parcel Info
City/State/Zip:
FRISCO, TX, 75035
Subdivision:
ALEXAN FRISCO (CFR)
|
| APPLICANT | Claudio Campos | (469)317-2261 | claudio@hlrinc.net | 14881 Quorum Dr. | Dallas, TX 75254 |
| OWNER | ABL APARTMENTS VENTURE LLC | ()- | | | DALLAS, TX 75219-3916 |
| CONTRACTOR | MAPLE MULTI-FAMILY CONTRACTORS LLC | (972)955-0117 | tbreaux@tcr.com | 3889 Maple Ave. | Dallas, TX 75219 |
| ELECT. CTR. | MCPHERSON ELECTRIC INC | (972)845-2429 | OFFICE@SUCCESSPAYS.COM | 1640 SLATE ROCK RD | ENNIS, TX 75119 |
| MECH. CTR. | SCHAFFER MECHANICAL | (713)669-0099 | CLAUDIA@SCHAFFERMECH.COM | 5420 GULFTON DRIVE | HOUSTON, TX 77081 |
| PLUM. CTR. | INFINITY PLUMBING, INC | (972)938-3030 | lisamilholen@infinityplumbing.net | PO BOX 936 | WAXAHACHIE, TX 75168 |
|
| SLAB COMM 08/01/2023 DC2 |
$35.00
|
3/26/2024
|
| PERCENT CREDIT CARD FEE |
$1.30
|
3/26/2024
|
| PERCENT CREDIT CARD FEE |
$68.20
|
4/24/2024
|
| PERCENT CREDIT CARD FEE |
$2.80
|
6/28/2024
|
| PERCENT CREDIT CARD FEE |
$1.40
|
7/29/2024
|
| PERCENT CREDIT CARD FEE |
$0.70
|
8/26/2024
|
| PERCENT CREDIT CARD FEE |
$3.40
|
10/10/2024
|
| PERCENT CREDIT CARD FEE |
$1.40
|
3/26/2025
|
| PERCENT CREDIT CARD FEE |
$0.70
|
4/25/2025
|
| PERCENT CREDIT CARD FEE |
$0.70
|
5/2/2025
|
| PERCENT CREDIT CARD FEE |
$0.70
|
5/28/2025
|
| FRAME COMM 08/07/2024 JDW2 |
$35.00
|
8/26/2024
|
| DRYWALL COMM 10/01/2024 JDW2 |
$35.00
|
10/10/2024
|
| MECHANICAL ROUGH 06/14/2024 JWR |
$35.00
|
6/28/2024
|
| AUTO PROCESSING FEE |
$6.00
|
5/19/2022
|
| COMMERCIAL FEE |
$27,668.92
|
12/20/2022
|
| COMMERCIAL BUILDING PERMIT FEE |
$224,197.14
|
12/20/2022
|
| COMMERCIAL MECHANICAL FEE |
$34,578.65
|
12/20/2022
|
| COMMERCIAL NEW APPLICATION FEE |
$300.00
|
5/19/2022
|
| COMMERCIAL PLUMBING FEE |
$62,217.57
|
12/20/2022
|
| SEWER IMPACT FEE |
$287,928.00
|
12/20/2022
|
| THOROUGHFARE IMPACT FEE |
$0.00
|
|
| WATER IMPACT FEE |
$270,098.00
|
12/20/2022
|
| BRICKWALL TIE COMM 06/21/2024 PJF |
$35.00
|
6/28/2024
|
| BRICKWALL TIE COMM 06/21/2024 PJF |
$35.00
|
6/28/2024
|
| DRYWALL COMM 06/19/2024 PJF |
$35.00
|
6/28/2024
|
| FRAME COMM 07/12/2024 PJF |
$35.00
|
7/29/2024
|
| CEILING 07/16/2024 PJF |
$35.00
|
7/29/2024
|
| FRAME COMM 09/04/2024 PJF |
$30.00
|
10/10/2024
|
| DRYWALL COMM 09/06/2024 PJF |
$35.00
|
10/10/2024
|
| FRAME COMM 09/17/2024 PJF |
$35.00
|
10/10/2024
|
| DRYWALL COMM 10/10/2024 PJF |
$35.00
|
10/10/2024
|
| ELECT FINAL COMM 02/26/2025 PJF |
$35.00
|
3/26/2025
|
| LIFESAFETY 03/11/2025 PJF |
$35.00
|
3/26/2025
|
| ELECT FINAL COMM 04/01/2025 PJF |
$35.00
|
4/25/2025
|
| LIFESAFETY 04/30/2025 PJF |
$35.00
|
5/2/2025
|
| ELECT FINAL COMM 05/23/2025 PJF |
$35.00
|
5/28/2025
|
| PLUMBING ROUGH-IN 06/08/2023 SDC |
$30.00
|
3/26/2024
|
| MECHANICAL ROUGH 10/01/2024 SMH |
$0.00
|
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| WATER METER DEPOSIT COMMERCIAL |
$13,200.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| 3 INCH COMP METER |
$3,225.00
|
4/19/2024
|
| WATER METER DEPOSIT COMMERCIAL |
$2,200.00
|
4/24/2024
|
| 1 INCH PD METER |
$1,210.00
|
4/24/2024
|
| Total Fees |
|
Charged: $963,040.58
Balance Due: $0.00
|
|
| COMM CO | APPROVED |
8/29/2025
| | 8/29/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
8/28/2025
| | 8/28/2025 | |
More Info
|
| COMM CO | TEMP CO |
8/28/2025
| | 8/28/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
8/28/2025
| | 8/28/2025 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
8/27/2025
| | 8/27/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/27/2025
| | 8/27/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
8/26/2025
| | 8/26/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/26/2025
| | 8/26/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/26/2025
| | 8/26/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
8/25/2025
| | 8/25/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
8/25/2025
| 9:00 AM | 8/25/2025 | 11:00 AM |
More Info
|
| ELECT FINAL COMM | APPROVED |
8/20/2025
| | 8/20/2025 | |
More Info
|
| PLUMBING FINAL | CANCELLED |
8/20/2025
| | 8/20/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
8/15/2025
| | 8/15/2025 | |
More Info
|
| COMM CO | TEMP CO |
8/15/2025
| | 8/15/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
8/14/2025
| 9:00 AM | 8/14/2025 | 10:00 AM |
More Info
|
| ELECT FINAL COMM | APPROVED |
8/14/2025
| | 8/14/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/14/2025
| | 8/14/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
8/14/2025
| | 8/14/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
8/13/2025
| | 8/13/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/13/2025
| | 8/13/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
8/12/2025
| | 8/12/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
8/12/2025
| | 8/12/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
8/6/2025
| | 8/6/2025 | |
More Info
|
| COMM CO | TEMP CO |
8/5/2025
| | 8/5/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
8/4/2025
| | 8/4/2025 | |
More Info
|
| GAS RELEASE | APPROVED |
8/1/2025
| | 8/1/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
7/30/2025
| | 7/30/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
7/30/2025
| | 7/30/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/30/2025
| | 7/30/2025 | |
More Info
|
| FIRE FINAL | |
7/29/2025
| 9:00 AM | | |
More Info
|
| FIRE FINAL | APPROVED |
7/29/2025
| 9:00 AM | 7/29/2025 | |
More Info
|
| GAS RELEASE | COMM FAILED |
7/24/2025
| | 7/24/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
7/23/2025
| | 7/23/2025 | |
More Info
|
| COMM CO | TEMP CO |
7/23/2025
| | 7/23/2025 | |
More Info
|
| BUILDING FINAL | COMM FAILED |
7/22/2025
| | 7/22/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
7/21/2025
| | 7/21/2025 | |
More Info
|
| SET 1 PD METER | APPROVED |
7/21/2025
| 8:30 AM | 7/21/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
7/17/2025
| | 7/17/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
7/17/2025
| 1:30 PM | 7/17/2025 | 2:00 PM |
More Info
|
| FIRE FINAL | CANCELLED |
7/17/2025
| 1:30 PM | 7/17/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
7/14/2025
| | 7/14/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/14/2025
| | 7/14/2025 | |
More Info
|
| COMM CO | TEMP CO |
7/10/2025
| | 7/10/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
7/8/2025
| | 7/8/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/8/2025
| | 7/8/2025 | |
More Info
|
| COMM CO | TEMP CO |
7/3/2025
| | 6/19/2025 | |
More Info
|
| ELECT FINAL COMM | COMM FAILED |
6/27/2025
| | 6/27/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
6/26/2025
| | 6/26/2025 | |
More Info
|
| GAS PRESSURE | APPROVED |
6/25/2025
| | 6/25/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
6/25/2025
| | 6/25/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
6/19/2025
| | 6/19/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
6/19/2025
| | 6/19/2025 | |
More Info
|
| PLUMBING FINAL | CANCELLED |
6/19/2025
| | 6/19/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
6/17/2025
| | 6/17/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
6/17/2025
| 1:30 PM | 6/17/2025 | 2:00 PM |
More Info
|
| LIFESAFETY | APPROVED |
6/17/2025
| | 6/17/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
6/13/2025
| | 6/13/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
6/13/2025
| | 6/13/2025 | |
More Info
|
| PIER COMM | CANCELLED |
6/12/2025
| | 6/12/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
6/9/2025
| | 6/9/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
6/9/2025
| | 6/9/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
6/6/2025
| | 6/6/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
6/5/2025
| | 6/5/2025 | |
More Info
|
| COMM CO | TEMP CO |
6/3/2025
| | 6/3/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
5/29/2025
| | 5/29/2025 | |
More Info
|
| INSPECTION ASSIST | COMPLETED |
5/28/2025
| 9:00 AM | 5/28/2025 | |
More Info
|
| INSPECTION ASSIST | |
5/27/2025
| | | |
More Info
|
| FIRE FINAL | APPROVED |
5/27/2025
| 9:00 AM | 5/27/2025 | 9:30 AM |
More Info
|
| INSPECTION ASSIST | COMPLETED |
5/27/2025
| 9:00 AM | 5/27/2025 | |
More Info
|
| ELECT FINAL COMM | COMM FAILED |
5/23/2025
| | 5/23/2025 | |
More Info
|
| LIFESAFETY | COMM FAILED |
5/23/2025
| | 5/23/2025 | |
More Info
|
| FOOTINGS COMM | APPROVED |
5/22/2025
| | 5/22/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
5/21/2025
| | 5/21/2025 | |
More Info
|
| GAS RELEASE | APPROVED |
5/21/2025
| | 5/21/2025 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
5/14/2025
| | 5/14/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
5/8/2025
| | 5/8/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
5/8/2025
| | 5/8/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
5/6/2025
| | 5/6/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
5/6/2025
| | 5/6/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
5/6/2025
| | 5/6/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
5/5/2025
| | 5/5/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
5/5/2025
| | 5/5/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
5/2/2025
| | 5/2/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
5/2/2025
| | 5/2/2025 | |
More Info
|
| COMM CO | TEMP CO |
5/2/2025
| | 5/2/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
5/1/2025
| 1:30 PM | 5/1/2025 | 2:30 PM |
More Info
|
| FIRE FINAL | APPROVED |
5/1/2025
| 1:30 PM | 5/1/2025 | 2:30 PM |
More Info
|
| ELECT ROUGH COMM | APPROVED |
4/30/2025
| | 4/29/2025 | |
More Info
|
| SLAB COMM | APPROVED |
4/30/2025
| | 4/29/2025 | |
More Info
|
| LIFESAFETY | COMM FAILED |
4/30/2025
| | 4/30/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
4/29/2025
| | 4/29/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
4/25/2025
| | 4/25/2025 | |
More Info
|
| COMM CO | TEMP CO |
4/25/2025
| | 4/25/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
4/24/2025
| | 4/24/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
4/22/2025
| 1:00 PM | 4/22/2025 | 1:45 PM |
More Info
|
| MECHANICAL FINAL | APPROVED |
4/22/2025
| | 4/22/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
4/22/2025
| | 4/22/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
4/21/2025
| | 4/21/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
4/21/2025
| | 4/21/2025 | |
More Info
|
| LIFESAFETY | APPROVED |
4/16/2025
| | 4/16/2025 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
4/16/2025
| | 4/16/2025 | |
More Info
|
| PLUMBING FINAL | CANCELLED |
4/16/2025
| | 4/16/2025 | |
More Info
|
| MECHANICAL FINAL | CANCELLED |
4/16/2025
| | 4/16/2025 | |
More Info
|
| LIFESAFETY | APPROVED |
4/15/2025
| | 4/15/2025 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
4/15/2025
| | 4/15/2025 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
4/15/2025
| | 4/15/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
4/9/2025
| | 4/9/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
4/8/2025
| | 4/8/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
4/8/2025
| | 4/8/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
4/3/2025
| | 4/3/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
4/3/2025
| | 4/3/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
4/2/2025
| | 4/2/2025 | |
More Info
|
| ELECT FINAL COMM | COMM FAILED |
4/1/2025
| | 4/1/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
4/1/2025
| | 4/1/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
4/1/2025
| | 4/1/2025 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
3/28/2025
| | 3/28/2025 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
3/28/2025
| | 3/28/2025 | |
More Info
|
| COMM CO | TEMP CO |
3/26/2025
| | 3/26/2025 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/25/2025
| | 3/25/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
3/24/2025
| | 3/24/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
3/24/2025
| | 3/24/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
3/24/2025
| | 3/24/2025 | |
More Info
|
| BUILDING FINAL | APPROVED |
3/24/2025
| | 3/24/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
3/21/2025
| 1:30 PM | 3/21/2025 | 2:30 PM |
More Info
|
| FIRE FINAL | APPROVED |
3/21/2025
| 1:30 PM | 3/21/2025 | 2:30 PM |
More Info
|
| LIFESAFETY | APPROVED |
3/19/2025
| | 3/19/2025 | |
More Info
|
| LIFESAFETY | APPROVED |
3/19/2025
| | 3/19/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
3/17/2025
| | 3/17/2025 | |
More Info
|
| FIRE FINAL | APPROVED |
3/14/2025
| 10:00 AM | 3/14/2025 | 11:00 AM |
More Info
|
| FIRE FINAL | APPROVED |
3/14/2025
| 10:00 AM | 3/14/2025 | 11:00 AM |
More Info
|
| LIFESAFETY | APPROVED |
3/13/2025
| | 3/13/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
3/13/2025
| | 3/13/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
3/12/2025
| | 3/12/2025 | |
More Info
|
| LIFESAFETY | COMM FAILED |
3/11/2025
| | 3/11/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
3/11/2025
| | 3/11/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
3/11/2025
| | 3/11/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
3/4/2025
| | 3/4/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
3/4/2025
| | 3/4/2025 | |
More Info
|
| LIFESAFETY | APPROVED |
3/3/2025
| | 3/3/2025 | |
More Info
|
| ELECT FINAL COMM | COMM FAILED |
2/26/2025
| | 2/26/2025 | |
More Info
|
| FIRE FINAL | CANCELLED |
2/26/2025
| 1:30 PM | 2/27/2025 | |
More Info
|
| ELECT RELEASE COMM | CANCELLED |
2/21/2025
| | 2/21/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
2/21/2025
| | 2/21/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
2/18/2025
| | 2/18/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
2/18/2025
| | 2/18/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
2/17/2025
| | 2/17/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
2/17/2025
| | 2/17/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
2/14/2025
| | 2/14/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
2/14/2025
| | 2/14/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
2/12/2025
| | 2/12/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
2/7/2025
| | 2/7/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
2/6/2025
| | 2/6/2025 | |
More Info
|
| FIRE FINAL | FIRE FAILED |
2/4/2025
| 9:00 AM | 2/4/2025 | 11:00 AM |
More Info
|
| LIFESAFETY | CANCELLED |
2/4/2025
| | 2/4/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
1/31/2025
| | 1/31/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
1/31/2025
| | 1/31/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
1/29/2025
| | 1/29/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
1/29/2025
| | 1/29/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
1/28/2025
| | 1/28/2025 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
1/27/2025
| | 1/27/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
1/27/2025
| | 1/27/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
1/24/2025
| | 1/24/2025 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
1/23/2025
| | 1/23/2025 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
1/23/2025
| | 1/23/2025 | |
More Info
|
| PLUMBING FINAL | APPROVED |
1/23/2025
| | 1/23/2025 | |
More Info
|
| FIREINSULATION | |
1/22/2025
| 1:30 PM | | |
More Info
|
| ELECT FINAL COMM | APPROVED |
1/22/2025
| | 1/22/2025 | |
More Info
|
| PIER COMM | APPROVED |
1/22/2025
| | 1/22/2025 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
1/17/2025
| | 1/17/2025 | |
More Info
|
| DRYWALL COMM | APPROVED |
1/7/2025
| | 1/7/2025 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/30/2024
| | 12/30/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/26/2024
| | 12/26/2024 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
12/23/2024
| | 12/23/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/20/2024
| | 12/20/2024 | |
More Info
|
| PIER COMM | APPROVED |
12/19/2024
| | 12/19/2024 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
12/18/2024
| | 12/18/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
12/18/2024
| | 12/18/2024 | |
More Info
|
| PLUMBING FINAL | APPROVED |
12/18/2024
| | 12/18/2024 | |
More Info
|
| PLUMBING FINAL | APPROVED |
12/18/2024
| | 12/18/2024 | |
More Info
|
| PLUMBING FINAL | CANCELLED |
12/16/2024
| | 12/16/2024 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
12/13/2024
| | 12/13/2024 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
12/10/2024
| | 12/10/2024 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
12/10/2024
| | 12/10/2024 | |
More Info
|
| CEILING | APPROVED |
12/9/2024
| | 12/9/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
12/9/2024
| | 12/9/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/4/2024
| | 12/4/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
12/4/2024
| | 12/4/2024 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
12/3/2024
| | 12/3/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/2/2024
| | 12/2/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
12/2/2024
| | 12/2/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
12/2/2024
| | 12/2/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
11/27/2024
| 8:30 AM | 11/27/2024 | 9:00 AM |
More Info
|
| ELECT FINAL COMM | APPROVED |
11/26/2024
| | 11/26/2024 | |
More Info
|
| MECHANICAL FINAL | COMM FAILED |
11/26/2024
| | 11/26/2024 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
11/26/2024
| | 11/26/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/25/2024
| | 11/25/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
11/22/2024
| | 11/22/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/19/2024
| | 11/19/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/18/2024
| | 11/18/2024 | |
More Info
|
| DRYWALL COMM | PARTIAL APPROVAL |
11/15/2024
| | 11/15/2024 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
11/15/2024
| | 11/15/2024 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
11/14/2024
| | 11/14/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/13/2024
| | 11/13/2024 | |
More Info
|
| FRAME COMM | APPROVED |
11/13/2024
| | 11/13/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
11/12/2024
| | 11/12/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
11/12/2024
| | 11/12/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/12/2024
| | 11/12/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
11/12/2024
| | 11/12/2024 | |
More Info
|
| FRAME COMM | APPROVED |
11/12/2024
| | 11/12/2024 | |
More Info
|
| FRAME COMM | APPROVED |
11/11/2024
| | 11/11/2024 | |
More Info
|
| CEILING | APPROVED |
11/11/2024
| | 11/11/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
11/11/2024
| | 11/11/2024 | |
More Info
|
| LATH COMM | APPROVED |
11/11/2024
| | 11/11/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
11/8/2024
| | 11/8/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/7/2024
| | 11/7/2024 | |
More Info
|
| CEILING | APPROVED |
11/7/2024
| | 11/7/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/7/2024
| | 11/7/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
11/7/2024
| | 11/7/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
11/7/2024
| 2:00 PM | 11/7/2024 | 2:45 PM |
More Info
|
| CEILING | CANCELLED |
11/6/2024
| | 11/6/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/6/2024
| | 11/6/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/4/2024
| | 11/4/2024 | |
More Info
|
| GAS PRESSURE | APPROVED |
11/4/2024
| | 11/4/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
11/4/2024
| | 11/4/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
11/1/2024
| | 11/1/2024 | |
More Info
|
| CEILING | APPROVED |
10/31/2024
| | 10/31/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/31/2024
| | 10/31/2024 | |
More Info
|
| FRAME COMM | APPROVED |
10/30/2024
| | 10/30/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/30/2024
| | 10/30/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/30/2024
| | 10/30/2024 | |
More Info
|
| FRAME COMM | COMM FAILED |
10/29/2024
| | 10/29/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/29/2024
| | 10/29/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/29/2024
| | 10/29/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/28/2024
| | 10/28/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/25/2024
| | 10/25/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
10/25/2024
| 11:00 AM | 10/25/2024 | 11:30 AM |
More Info
|
| FRAME COMM | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| CEILING | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/24/2024
| | 10/24/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/23/2024
| | 10/23/2024 | |
More Info
|
| FRAME COMM | APPROVED |
10/23/2024
| | 10/23/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/23/2024
| | 10/23/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/23/2024
| | 10/23/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/22/2024
| | 10/22/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/22/2024
| | 10/22/2024 | |
More Info
|
| CEILING | APPROVED |
10/21/2024
| | 10/21/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/21/2024
| | 10/21/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
10/21/2024
| | 10/21/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/18/2024
| | 10/18/2024 | |
More Info
|
| SLAB COMM | APPROVED |
10/18/2024
| | 10/18/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/17/2024
| | 10/17/2024 | |
More Info
|
| FRAME COMM | RES FAILED |
10/17/2024
| | 10/17/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/17/2024
| | 10/17/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
10/16/2024
| 11:00 AM | 10/16/2024 | 11:30 AM |
More Info
|
| DRYWALL COMM | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| GAS PRESSURE | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/16/2024
| | 10/16/2024 | |
More Info
|
| DRYWALL COMM | CANCELLED |
10/15/2024
| | 10/15/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/15/2024
| | 10/15/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
10/15/2024
| | 10/15/2024 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
10/15/2024
| | 10/15/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/15/2024
| | 10/15/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
10/11/2024
| | 10/11/2024 | |
More Info
|
| GAS PRESSURE | COMM FAILED |
10/11/2024
| | 10/11/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/11/2024
| | 10/11/2024 | |
More Info
|
| DRYWALL COMM | COMM FAILED |
10/10/2024
| | 10/10/2024 | |
More Info
|
| CEILING | APPROVED |
10/10/2024
| | 10/10/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/10/2024
| | 10/10/2024 | |
More Info
|
| DRYWALL COMM | CANCELLED |
10/10/2024
| | 10/10/2024 | |
More Info
|
| FRAME COMM | APPROVED |
10/9/2024
| | 10/9/2024 | |
More Info
|
| FRAME COMM | APPROVED |
10/8/2024
| | 10/8/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/8/2024
| | 10/8/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/8/2024
| | 10/8/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
10/8/2024
| | 10/8/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/8/2024
| | 10/8/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/7/2024
| | 10/7/2024 | |
More Info
|
| CEILING | APPROVED |
10/7/2024
| | 10/7/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
10/7/2024
| | 10/7/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
10/7/2024
| 9:00 AM | 10/7/2024 | 9:45 AM |
More Info
|
| DRYWALL COMM | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| LATH COMM | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/3/2024
| | 10/3/2024 | |
More Info
|
| FRAME COMM | APPROVED |
10/2/2024
| | 10/2/2024 | |
More Info
|
| DRYWALL COMM | COMM FAILED |
10/1/2024
| | 10/1/2024 | |
More Info
|
| DRYWALL COMM | COMM FAILED |
10/1/2024
| | 10/1/2024 | |
More Info
|
| FRAME COMM | CANCELLED |
10/1/2024
| | 10/1/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
10/1/2024
| | 10/1/2024 | |
More Info
|
| INSULATION COMM | PARTIAL APPROVAL |
10/1/2024
| | 10/1/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
10/1/2024
| | 10/1/2024 | |
More Info
|
| GAS PRESSURE | COMM FAILED |
9/26/2024
| | 9/26/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/26/2024
| | 9/26/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/26/2024
| | 9/26/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/24/2024
| | 9/24/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
9/24/2024
| | 9/24/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/23/2024
| | 9/23/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
9/23/2024
| 1:30 PM | 9/23/2024 | 2:00 PM |
More Info
|
| DRYWALL COMM | APPROVED |
9/23/2024
| | 9/23/2024 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
9/23/2024
| | 9/23/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/23/2024
| | 9/23/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/23/2024
| | 9/23/2024 | |
More Info
|
| PIER COMM | APPROVED |
9/20/2024
| | 9/20/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/19/2024
| | 9/19/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
9/19/2024
| 1:30 PM | 9/19/2024 | 2:00 PM |
More Info
|
| INSULATION COMM | APPROVED |
9/19/2024
| | 9/19/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/19/2024
| | 9/19/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/19/2024
| | 9/19/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/18/2024
| | 9/18/2024 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
9/17/2024
| | 9/17/2024 | |
More Info
|
| DRYWALL COMM | PARTIAL APPROVAL |
9/17/2024
| | 9/17/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/17/2024
| | 9/17/2024 | |
More Info
|
| MECHANICAL ROUGH | CANCELLED |
9/17/2024
| | 9/17/2024 | |
More Info
|
| LATH COMM | APPROVED |
9/17/2024
| | 9/17/2024 | |
More Info
|
| FRAME COMM | COMM FAILED |
9/17/2024
| | 9/17/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/16/2024
| | 9/16/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
9/16/2024
| | 9/16/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/16/2024
| | 9/16/2024 | |
More Info
|
| LATH COMM | CANCELLED |
9/16/2024
| | 9/16/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/16/2024
| | 9/16/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/11/2024
| | 9/11/2024 | |
More Info
|
| CEILING | APPROVED |
9/10/2024
| | 9/10/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/10/2024
| | 9/10/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| LATH COMM | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
9/9/2024
| | 9/9/2024 | |
More Info
|
| DRYWALL COMM | COMM FAILED |
9/6/2024
| | 9/6/2024 | |
More Info
|
| BRICKWALL TIE COMM | CANCELLED |
9/6/2024
| | 9/6/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/6/2024
| | 9/6/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
9/6/2024
| | 9/6/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/6/2024
| | 9/6/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
9/5/2024
| 9:00 AM | 9/5/2024 | 9:45 AM |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
9/5/2024
| | 9/5/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
9/5/2024
| | 9/5/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/5/2024
| | 9/5/2024 | |
More Info
|
| FRAME COMM | APPROVED |
9/4/2024
| | 9/4/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
9/4/2024
| | 9/4/2024 | |
More Info
|
| MECHANICAL ROUGH | CANCELLED |
9/4/2024
| | 9/4/2024 | |
More Info
|
| FRAME COMM | COMM FAILED |
9/4/2024
| | 9/4/2024 | |
More Info
|
| CEILING | PARTIAL APPROVAL |
9/3/2024
| | 9/3/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
9/3/2024
| | 9/3/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
9/3/2024
| | 9/3/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/30/2024
| | 8/30/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/30/2024
| | 8/30/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| CEILING | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| LATH COMM | APPROVED |
8/29/2024
| | 8/29/2024 | |
More Info
|
| DRYWALL COMM | CANCELLED |
8/28/2024
| | 8/28/2024 | |
More Info
|
| DRYWALL COMM | CANCELLED |
8/28/2024
| | 8/28/2024 | |
More Info
|
| MECHANICAL ROUGH | CANCELLED |
8/28/2024
| | 8/28/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/26/2024
| | 8/26/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/26/2024
| | 8/26/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
8/26/2024
| | 8/26/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
8/26/2024
| | 8/26/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/23/2024
| | 8/23/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/23/2024
| | 8/23/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/21/2024
| | 8/21/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/21/2024
| | 8/21/2024 | |
More Info
|
| LATH COMM | APPROVED |
8/21/2024
| | 8/21/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/21/2024
| | 8/21/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/20/2024
| | 8/20/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
8/20/2024
| | 8/20/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
8/19/2024
| | 8/19/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
8/19/2024
| | 8/19/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/19/2024
| | 8/19/2024 | |
More Info
|
| LATH COMM | APPROVED |
8/19/2024
| | 8/19/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/19/2024
| | 8/19/2024 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
8/16/2024
| | 8/16/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/15/2024
| | 8/15/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/15/2024
| | 8/15/2024 | |
More Info
|
| CEILING | APPROVED |
8/14/2024
| | 8/14/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
8/14/2024
| 9:00 AM | 8/14/2024 | 9:30 AM |
More Info
|
| INSULATION COMM | APPROVED |
8/14/2024
| | 8/14/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/13/2024
| | 8/13/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/12/2024
| | 8/12/2024 | |
More Info
|
| LATH COMM | APPROVED |
8/12/2024
| | 8/12/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
8/9/2024
| | 8/9/2024 | |
More Info
|
| CEILING | APPROVED |
8/9/2024
| | 8/9/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/9/2024
| | 8/9/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
8/8/2024
| | 8/8/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/8/2024
| | 8/8/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
8/8/2024
| | 8/8/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
8/8/2024
| | 8/8/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
8/8/2024
| | 8/8/2024 | |
More Info
|
| DRYWALL COMM | CANCELLED |
8/7/2024
| | 8/7/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
8/7/2024
| | 8/7/2024 | |
More Info
|
| FRAME COMM | COMM FAILED |
8/7/2024
| | 8/7/2024 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
8/7/2024
| | 8/7/2024 | |
More Info
|
| MECHANICAL ROUGH | CANCELLED |
8/7/2024
| | 8/7/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
8/6/2024
| | 8/6/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
8/6/2024
| | 8/6/2024 | |
More Info
|
| DRYWALL COMM | PARTIAL APPROVAL |
8/5/2024
| | 8/5/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
8/5/2024
| | 8/2/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
8/5/2024
| | 8/5/2024 | |
More Info
|
| FRAME COMM | APPROVED |
8/5/2024
| | 8/5/2024 | |
More Info
|
| CEILING | APPROVED |
8/2/2024
| | 8/2/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
8/2/2024
| 8:30 AM | 8/2/2024 | 9:00 AM |
More Info
|
| SHEATHING COMM | APPROVED |
8/2/2024
| | 8/2/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/1/2024
| | 8/1/2024 | |
More Info
|
| DRYWALL COMM | PARTIAL APPROVAL |
8/1/2024
| | 8/1/2024 | |
More Info
|
| LATH COMM | APPROVED |
8/1/2024
| | 8/1/2024 | |
More Info
|
| INSULATION COMM | PARTIAL APPROVAL |
8/1/2024
| | 8/1/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/31/2024
| | 7/31/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/31/2024
| | 7/31/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/31/2024
| | 7/31/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/31/2024
| | 7/31/2024 | |
More Info
|
| CEILING | APPROVED |
7/30/2024
| | 7/30/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/30/2024
| | 7/30/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
7/29/2024
| 10:30 AM | 7/29/2024 | 11:30 AM |
More Info
|
| INSPECTION ASSIST | COMPLETED |
7/29/2024
| 10:30 AM | 7/29/2024 | 11:30 AM |
More Info
|
| FRAME COMM | APPROVED |
7/26/2024
| | 7/26/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
7/26/2024
| | 7/26/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/25/2024
| | 7/25/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/25/2024
| | 7/25/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
7/25/2024
| | 7/25/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/25/2024
| | 7/25/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/24/2024
| | 7/24/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/23/2024
| | 7/23/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
7/22/2024
| | 7/22/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/22/2024
| | 7/22/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/19/2024
| | 7/19/2024 | |
More Info
|
| CEILING | APPROVED |
7/19/2024
| | 7/19/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
7/19/2024
| | 7/19/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
7/19/2024
| 10:00 AM | 7/19/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/18/2024
| | 7/18/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/18/2024
| | 7/18/2024 | |
More Info
|
| INSULATION COMM | SEE NOTES |
7/18/2024
| | 7/18/2024 | |
More Info
|
| CEILING | APPROVED |
7/17/2024
| | 7/17/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
7/17/2024
| | 7/17/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/17/2024
| | 7/17/2024 | |
More Info
|
| CEILING | APPROVED |
7/17/2024
| | 7/17/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| CEILING | CANCELLED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| CEILING | COMM FAILED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/16/2024
| | 7/16/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/15/2024
| | 7/15/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/15/2024
| | 7/15/2024 | |
More Info
|
| FRAME COMM | COMM FAILED |
7/12/2024
| | 7/12/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/12/2024
| | 7/12/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
7/12/2024
| | 7/12/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/11/2024
| | 7/11/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
7/11/2024
| | 7/11/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/11/2024
| | 7/11/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/10/2024
| | 7/10/2024 | |
More Info
|
| CEILING | APPROVED |
7/9/2024
| | 7/9/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/8/2024
| | 7/8/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/8/2024
| | 7/8/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/3/2024
| | 7/3/2024 | |
More Info
|
| LATH COMM | APPROVED |
7/3/2024
| | 7/3/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
7/3/2024
| | 7/3/2024 | |
More Info
|
| CEILING | APPROVED |
7/2/2024
| | 7/2/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
7/2/2024
| | 7/2/2024 | |
More Info
|
| FRAME COMM | APPROVED |
7/1/2024
| | 7/1/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
7/1/2024
| 2:00 PM | 7/1/2024 | 2:30 PM |
More Info
|
| MECHANICAL ROUGH | APPROVED |
7/1/2024
| | 7/1/2024 | |
More Info
|
| INSPECTION ASSIST | COMPLETED |
7/1/2024
| 2:00 PM | 7/1/2024 | 2:30 PM |
More Info
|
| FRAME COMM | CANCELLED |
6/28/2024
| | 6/28/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
6/28/2024
| | 6/28/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/27/2024
| | 6/27/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/27/2024
| | 6/27/2024 | |
More Info
|
| FRAME COMM | APPROVED |
6/27/2024
| | 6/27/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
6/27/2024
| | 6/27/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
6/27/2024
| | 6/27/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
6/26/2024
| | 6/26/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/26/2024
| | 6/26/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/26/2024
| | 6/26/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/26/2024
| | 6/26/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/26/2024
| | 6/26/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
6/26/2024
| 1:30 PM | 6/26/2024 | |
More Info
|
| FRAME COMM | APPROVED |
6/25/2024
| | 6/25/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/25/2024
| | 6/25/2024 | |
More Info
|
| LATH COMM | APPROVED |
6/25/2024
| | 6/25/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/25/2024
| | 6/25/2024 | |
More Info
|
| CEILING | APPROVED |
6/24/2024
| | 6/24/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/24/2024
| | 6/24/2024 | |
More Info
|
| CEILING | COMM FAILED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| BRICKWALL TIE COMM | COMM FAILED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| BRICKWALL TIE COMM | COMM FAILED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
6/21/2024
| | 6/21/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
6/20/2024
| | 6/20/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
6/20/2024
| | 6/20/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
6/20/2024
| | 6/20/2024 | |
More Info
|
| DRYWALL COMM | COMM FAILED |
6/19/2024
| | 6/19/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/17/2024
| | 6/17/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
6/14/2024
| | 6/14/2024 | |
More Info
|
| MECHANICAL ROUGH | COMM FAILED |
6/14/2024
| | 6/14/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
6/14/2024
| | 6/14/2024 | |
More Info
|
| FRAME COMM | APPROVED |
6/13/2024
| | 6/13/2024 | |
More Info
|
| DRYWALL COMM | APPROVED |
6/13/2024
| | 6/13/2024 | |
More Info
|
| FRAME COMM | APPROVED |
6/12/2024
| | 6/12/2024 | |
More Info
|
| INSPECTION ASSIST | COMPLETED |
6/12/2024
| 9:00 AM | 6/12/2024 | 10:00 AM |
More Info
|
| INSULATION COMM | APPROVED |
6/12/2024
| | 6/12/2024 | |
More Info
|
| FIREINSULATION | APPROVED |
6/12/2024
| 9:00 AM | 6/12/2024 | 10:00 AM |
More Info
|
| FRAME COMM | APPROVED |
6/11/2024
| | 6/11/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/11/2024
| | 6/11/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/11/2024
| | 6/11/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/6/2024
| | 6/6/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
6/6/2024
| | 6/6/2024 | |
More Info
|
| SET 1 PD METER | APPROVED |
6/6/2024
| 8:15 AM | 6/6/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
6/5/2024
| | 6/5/2024 | |
More Info
|
| LATH COMM | APPROVED |
6/5/2024
| | 6/5/2024 | |
More Info
|
| MISC FRAME COMM | APPROVED |
6/4/2024
| | 6/4/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
6/3/2024
| | 6/3/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
6/3/2024
| | 6/3/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
6/3/2024
| | 6/3/2024 | |
More Info
|
| T-POLE COMM | APPROVED |
6/3/2024
| | 6/3/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
5/30/2024
| | 5/30/2024 | |
More Info
|
| FRAME COMM | APPROVED |
5/29/2024
| | 5/29/2024 | |
More Info
|
| INSULATION COMM | APPROVED |
5/29/2024
| | 5/29/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
5/28/2024
| | 5/28/2024 | |
More Info
|
| FRAME COMM | APPROVED |
5/24/2024
| | 5/24/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
5/24/2024
| | 5/24/2024 | |
More Info
|
| FRAME COMM | APPROVED |
5/23/2024
| | 5/23/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
5/23/2024
| | 5/23/2024 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
5/16/2024
| | 5/16/2024 | |
More Info
|
| CEILING | APPROVED |
5/14/2024
| | 5/14/2024 | |
More Info
|
| CEILING | CANCELLED |
5/13/2024
| | 5/13/2024 | |
More Info
|
| LATH COMM | APPROVED |
5/13/2024
| | 5/13/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
5/9/2024
| | 5/9/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
5/8/2024
| | 5/8/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
5/7/2024
| | 5/7/2024 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
5/7/2024
| | 5/7/2024 | |
More Info
|
| MECHANICAL ROUGH | PARTIAL APPROVAL |
5/6/2024
| | 5/6/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
5/3/2024
| | 5/3/2024 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
5/2/2024
| | 5/2/2024 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
5/2/2024
| | 5/2/2024 | |
More Info
|
| METER PAYMENT | APPROVED |
4/24/2024
| | 4/24/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
4/24/2024
| | 4/24/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
4/24/2024
| | 4/24/2024 | |
More Info
|
| METER PAYMENT | APPROVED |
4/24/2024
| | 4/24/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| SET 3IN CMPND METER | APPROVED |
4/23/2024
| | 4/23/2024 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
4/22/2024
| | 4/22/2024 | |
More Info
|
| METER PAYMENT | APPROVED |
4/19/2024
| | 4/19/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
4/10/2024
| | 4/10/2024 | |
More Info
|
| SHEATHING COMM | COMM FAILED |
4/8/2024
| | 4/8/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
3/28/2024
| | 3/28/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
3/26/2024
| | 3/26/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
3/18/2024
| | 3/18/2024 | |
More Info
|
| FIRELANE INSPECTION | APPROVED |
3/5/2024
| 10:00 AM | 3/5/2024 | |
More Info
|
| SHEATHING COMM | APPROVED |
3/4/2024
| | 3/4/2024 | |
More Info
|
| PAVING | APPROVED |
1/4/2024
| | 1/4/2024 | |
More Info
|
| PAVING | CANCELLED |
1/3/2024
| | 1/3/2024 | |
More Info
|
| PAVING | CANCELLED |
1/2/2024
| | 1/2/2024 | |
More Info
|
| CONSTRUCTION SAFETY | COMPLETED |
12/18/2023
| 11:00 AM | 12/18/2023 | |
More Info
|
| PAVING | CANCELLED |
12/18/2023
| | 12/18/2023 | |
More Info
|
| FIRELANE INSPECTION | PARTIAL APPROVAL |
12/15/2023
| 10:00 AM | 12/15/2023 | |
More Info
|
| FRAME COMM | CANCELLED |
12/11/2023
| | 12/11/2023 | |
More Info
|
| PAVING | APPROVED |
12/8/2023
| | 12/8/2023 | |
More Info
|
| FIRELANE INSPECTION | CANCELLED |
12/7/2023
| 1:30 PM | 12/6/2023 | |
More Info
|
| PAVING | CANCELLED |
12/7/2023
| | 12/7/2023 | |
More Info
|
| PAVING | CANCELLED |
12/6/2023
| | 12/6/2023 | |
More Info
|
| PAVING | APPROVED |
12/1/2023
| | 12/1/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/28/2023
| | 11/28/2023 | |
More Info
|
| PAVING | APPROVED |
11/28/2023
| | 11/28/2023 | |
More Info
|
| PAVING | APPROVED |
11/21/2023
| | 11/21/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/20/2023
| | 11/20/2023 | |
More Info
|
| PAVING | APPROVED |
11/20/2023
| | 11/20/2023 | |
More Info
|
| FIRELANE INSPECTION | PARTIAL APPROVAL |
11/17/2023
| 1:00 PM | 11/17/2023 | |
More Info
|
| PAVING | APPROVED |
11/15/2023
| | 11/15/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
11/6/2023
| | 11/6/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/23/2023
| | 10/23/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/18/2023
| | 10/18/2023 | |
More Info
|
| PAVING | APPROVED |
10/16/2023
| | 10/16/2023 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
10/13/2023
| | 10/13/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/12/2023
| | 10/12/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/10/2023
| | 10/10/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/6/2023
| | 10/6/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
10/4/2023
| | 10/4/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/28/2023
| | 9/28/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/28/2023
| | 9/28/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/26/2023
| | 9/26/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
9/22/2023
| | 9/22/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/18/2023
| | 9/18/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/18/2023
| | 9/18/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/18/2023
| | 9/18/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/12/2023
| | 9/12/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
9/11/2023
| | 9/11/2023 | |
More Info
|
| SLAB COMM | APPROVED |
9/7/2023
| | 9/7/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
| SLAB COMM | CANCELLED |
8/24/2023
| | 8/24/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/24/2023
| | 8/24/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/21/2023
| | 8/21/2023 | |
More Info
|
| SLAB COMM | COMM FAILED |
8/17/2023
| | 8/17/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/17/2023
| | 8/17/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/15/2023
| | 8/15/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/14/2023
| | 8/14/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/11/2023
| | 8/11/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/11/2023
| | 8/11/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/10/2023
| | 8/10/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/8/2023
| | 8/8/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/7/2023
| | 8/7/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
8/2/2023
| | 8/2/2023 | |
More Info
|
| SLAB COMM | APPROVED |
8/2/2023
| | 8/2/2023 | |
More Info
|
| SLAB COMM | COMM FAILED |
8/1/2023
| | 8/1/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/31/2023
| | 7/31/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
7/31/2023
| | 7/31/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/25/2023
| | 7/25/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/25/2023
| | 7/25/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/24/2023
| | 7/24/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/24/2023
| | 7/24/2023 | |
More Info
|
| SLAB COMM | CANCELLED |
7/24/2023
| | 7/24/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
7/21/2023
| | 7/21/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/20/2023
| | 7/20/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/20/2023
| | 7/20/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
7/18/2023
| | 7/18/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
7/17/2023
| | 7/17/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/17/2023
| | 7/17/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/17/2023
| | 7/17/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
7/13/2023
| | 7/13/2023 | |
More Info
|
| SLAB COMM | APPROVED |
7/13/2023
| | 7/13/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
7/12/2023
| | 7/12/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/11/2023
| | 7/11/2023 | |
More Info
|
| SLAB COMM | CANCELLED |
7/11/2023
| | 7/11/2023 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
7/10/2023
| | 7/10/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
7/10/2023
| | 7/10/2023 | |
More Info
|
| SLAB COMM | CANCELLED |
7/10/2023
| | 7/10/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/29/2023
| | 6/29/2023 | |
More Info
|
| SLAB COMM | APPROVED |
6/29/2023
| | 6/29/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/27/2023
| | 6/27/2023 | |
More Info
|
| SLAB COMM | APPROVED |
6/27/2023
| | 6/27/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/26/2023
| | 6/26/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/21/2023
| | 6/21/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/21/2023
| | 6/21/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/14/2023
| | 6/14/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/14/2023
| | 6/14/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/14/2023
| | 6/14/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/14/2023
| | 6/14/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/13/2023
| | 6/13/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/12/2023
| | 6/12/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/12/2023
| | 6/12/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
6/9/2023
| | 6/9/2023 | |
More Info
|
| PLUMBING ROUGH-IN | RES FAILED |
6/8/2023
| | 6/8/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/6/2023
| | 6/6/2023 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
6/5/2023
| | 6/5/2023 | |
More Info
|
There are currently no reviews on this record.