Permit Info
Short Description:
365199 SF, NEWMAN PLACE
Expiration Date:
6/4/2024
Parcel Info
City/State/Zip:
FRISCO, TX, 75033
|
APPLICANT | lial wagner | (214)882-1728 | sonny.wagner@westwood-builders.com | 3198 Parkwood Blvd. , ste11076 | Frisco, TX 75034 |
OWNER | FRISCO LAND & CATTLE CO LP | ()- | | | FRISCO, TX 75033 |
CONTRACTOR | WESTWOOD RESIDENTIAL BUILDERS | (972)292-7660 | frank.chapa@westwood-builders.com | 3198 PARKWOOD BLVD | FRISCO, TX 75034 |
MECH. CTR. | HR MECHANICAL LLC | (832)864-3548 | go4hrmechanical@gmail.com | 19 HARBOUR DR | HOUSTON, TX 77058 |
PLUM. CTR. | PLUMBFAST MECHANICAL | (214)388-9011 | plumbfastmech@sbcglobal.net | 779 JUSTIN ROAD | ROCKWALL, TX 75087 |
PROP OWNER | Specified Properties LXXIX, LP | ()- | | 3198 PARKWOOD BLVD | FRISCO, TX 75034 |
|
T-POLE COMM 11/15/2022 DC2 |
$30.00
|
3/16/2023
|
FRAME COMM 03/03/2023 DC2 |
$35.00
|
3/16/2023
|
DRYWALL COMM 03/22/2023 DC2 |
$30.00
|
4/11/2023
|
FRAME COMM 03/31/2023 DC2 |
$35.00
|
4/11/2023
|
DRYWALL COMM 04/04/2023 DC2 |
$30.00
|
4/11/2023
|
ELECT ROUGH COMM 04/10/2023 DC2 |
$30.00
|
4/11/2023
|
DRYWALL COMM 04/19/2023 DC2 |
$35.00
|
5/18/2023
|
FRAME COMM 05/12/2023 DC2 |
$35.00
|
5/18/2023
|
DRYWALL COMM 05/15/2023 DC2 |
$35.00
|
5/18/2023
|
BRICKWALL TIE COMM 05/15/2023 DC2 |
$35.00
|
5/18/2023
|
BRICKWALL TIE COMM 05/18/2023 DC2 |
$35.00
|
5/18/2023
|
FRAME COMM 05/24/2023 DC2 |
$35.00
|
6/5/2023
|
FRAME COMM 05/30/2023 DC2 |
$30.00
|
6/5/2023
|
FRAME COMM 07/06/2023 DC2 |
$35.00
|
8/16/2023
|
INSULATION COMM 08/01/2023 DC2 |
$35.00
|
8/16/2023
|
ELECT FINAL COMM 08/14/2023 DC2 |
$35.00
|
8/16/2023
|
PERCENT CREDIT CARD FEE |
$2.00
|
3/16/2023
|
PERCENT CREDIT CARD FEE |
$3.20
|
4/11/2023
|
PERCENT CREDIT CARD FEE |
$3.50
|
5/18/2023
|
PERCENT CREDIT CARD FEE |
$7.50
|
6/5/2023
|
PERCENT CREDIT CARD FEE |
$12.10
|
8/16/2023
|
REPLACE READABLE REGISTER |
$310.00
|
6/5/2023
|
REPLACE DAMAGED/UNREADABLE REGISTER |
$500.00
|
8/16/2023
|
2 INCH T-10 METER |
$4,000.00
|
3/22/2023
|
WATER METER DEPOSIT COMMERCIAL |
$4,400.00
|
3/22/2023
|
AUTO PROCESSING FEE |
$6.00
|
9/27/2021
|
COMMERCIAL FEE |
$14,637.96
|
1/20/2022
|
COMMERCIAL BUILDING PERMIT FEE |
$86,227.14
|
1/20/2022
|
COMMERCIAL MECHANICAL FEE |
$18,289.95
|
1/20/2022
|
COMMERCIAL NEW APPLICATION FEE |
$300.00
|
9/27/2021
|
COMMERCIAL PLUMBING FEE |
$32,897.91
|
1/20/2022
|
SEWER IMPACT FEE |
$92,998.00
|
1/20/2022
|
THOROUGHFARE IMPACT FEE |
$185,996.00
|
1/20/2022
|
WATER IMPACT FEE |
$92,998.00
|
1/20/2022
|
PLUMB TOP OUT COMM 03/10/2023 SDC |
$35.00
|
3/16/2023
|
PLUMBING ROUGH-IN 03/30/2023 SDC |
$35.00
|
4/11/2023
|
2 INCH T-10 METER |
$2,475.00
|
12/9/2022
|
WATER METER DEPOSIT COMMERCIAL |
$3,300.00
|
12/9/2022
|
Total Fees |
Charged: $539,969.26
Balance Due: $0.00
|
|
COMM CO | |
1/2/2024
| | | |
More Info
|
COMM CO | COMM FAILED |
12/7/2023
| | 12/7/2023 | |
More Info
|
COMM CO | TEMP CO |
12/1/2023
| | 12/1/2023 | |
More Info
|
COMM CO | CANCELLED |
11/30/2023
| | 11/30/2023 | |
More Info
|
FIRE FINAL | APPROVED |
11/30/2023
| 9:30 AM | 11/30/2023 | |
More Info
|
COMM CO | TEMP CO |
11/15/2023
| | 11/15/2023 | |
More Info
|
FIRE FINAL | TEMP FIRE |
11/13/2023
| 3:00 PM | 11/13/2023 | |
More Info
|
COMM CO | TEMP CO |
11/10/2023
| | 11/10/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
11/9/2023
| | 11/9/2023 | |
More Info
|
FIRE FINAL | TEMP FIRE |
11/9/2023
| 9:00 AM | 11/9/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
11/8/2023
| | 11/8/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
11/8/2023
| | 11/8/2023 | |
More Info
|
BUILDING FINAL | COMM FAILED |
11/8/2023
| | 11/8/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
11/8/2023
| | 11/8/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
11/7/2023
| | 11/7/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
11/7/2023
| | 11/7/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
11/7/2023
| | 11/7/2023 | |
More Info
|
BUILDING FINAL | CANCELLED |
11/6/2023
| | 11/6/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
11/6/2023
| | 11/6/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/31/2023
| | 10/31/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/31/2023
| | 10/31/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/31/2023
| | 10/31/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/27/2023
| | 10/27/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/27/2023
| | 10/27/2023 | |
More Info
|
BUILDING FINAL | REVOKE PREV APPROVAL |
10/27/2023
| | 10/27/2023 | |
More Info
|
BUILDING FINAL | COMM FAILED |
10/26/2023
| | 10/26/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
10/24/2023
| | 10/24/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
10/24/2023
| | 10/24/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
10/24/2023
| | 10/24/2023 | |
More Info
|
MECHANICAL FINAL | RES FAILED |
10/23/2023
| | 10/23/2023 | |
More Info
|
BUILDING FINAL | APPROVED |
10/23/2023
| | 10/23/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
10/18/2023
| | 10/18/2023 | |
More Info
|
FLATWORK COMM | APPROVED |
10/17/2023
| | 10/17/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
10/17/2023
| | 10/17/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
10/16/2023
| | 10/16/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
10/12/2023
| | 10/12/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
10/12/2023
| | 10/12/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
10/12/2023
| | 10/12/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
10/11/2023
| | 10/11/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
10/11/2023
| | 10/11/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
10/10/2023
| | 10/10/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
10/10/2023
| | 10/10/2023 | |
More Info
|
FLATWORK COMM | APPROVED |
10/9/2023
| | 10/9/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
10/9/2023
| | 10/9/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
10/6/2023
| | 10/6/2023 | |
More Info
|
PLUMBING FINAL | COMM FAILED |
10/6/2023
| | 10/6/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
10/6/2023
| | 10/6/2023 | |
More Info
|
INSULATION COMM | APPROVED |
10/4/2023
| | 10/4/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
10/2/2023
| | 10/2/2023 | |
More Info
|
FIREINSULATION | APPROVED |
10/2/2023
| 1:30 PM | 10/3/2023 | |
More Info
|
FIRE FINAL | APPROVED |
9/29/2023
| 9:00 AM | 9/29/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
9/29/2023
| | 9/29/2023 | |
More Info
|
BUILDING FINAL | CANCELLED |
9/29/2023
| | 9/29/2023 | |
More Info
|
FIREINSULATION | APPROVED |
9/28/2023
| 1:30 PM | 9/28/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
9/28/2023
| | 9/28/2023 | |
More Info
|
INSULATION COMM | APPROVED |
9/28/2023
| | 9/28/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
9/26/2023
| | 9/26/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
9/26/2023
| | 9/26/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
9/25/2023
| | 9/25/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
9/21/2023
| | 9/21/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
9/21/2023
| | 9/21/2023 | |
More Info
|
FIREINSULATION | APPROVED |
9/21/2023
| 1:30 PM | 9/21/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
9/21/2023
| | 9/21/2023 | |
More Info
|
INSULATION COMM | APPROVED |
9/21/2023
| | 9/21/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
MECHANICAL FINAL | CANCELLED |
9/20/2023
| | 9/20/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
FRAME COMM | APPROVED |
9/20/2023
| | 9/20/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
9/19/2023
| | 9/19/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
9/19/2023
| | 9/19/2023 | |
More Info
|
INSULATION COMM | APPROVED |
9/19/2023
| | 9/19/2023 | |
More Info
|
FIREINSULATION | APPROVED |
9/19/2023
| 8:00 AM | 9/19/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
9/15/2023
| | 9/15/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
9/15/2023
| | 9/15/2023 | |
More Info
|
ELECT FINAL COMM | CANCELLED |
9/13/2023
| | 9/13/2023 | |
More Info
|
MEETING | |
9/13/2023
| 1:30 PM | | |
More Info
|
MECHANICAL FINAL | APPROVED |
9/13/2023
| | 9/13/2023 | |
More Info
|
MEETING | COMPLETED |
9/13/2023
| 1:30 PM | 9/13/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/12/2023
| | 9/12/2023 | |
More Info
|
PLUMBING FINAL | CANCELLED |
9/12/2023
| | 9/12/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/12/2023
| | 9/12/2023 | |
More Info
|
FRAME COMM | APPROVED |
9/12/2023
| | 9/12/2023 | |
More Info
|
FRAME COMM | APPROVED |
9/12/2023
| | 9/12/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
9/11/2023
| | 9/11/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
9/8/2023
| | 9/8/2023 | |
More Info
|
ELECT ROUGH COMM | CANCELLED |
9/8/2023
| | 9/8/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
9/8/2023
| | 9/8/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
9/7/2023
| | 9/7/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
9/7/2023
| | 9/7/2023 | |
More Info
|
ELECT FINAL COMM | CANCELLED |
9/6/2023
| | 9/6/2023 | |
More Info
|
FIREINSULATION | APPROVED |
9/6/2023
| 1:30 PM | 9/6/2023 | |
More Info
|
INSULATION COMM | APPROVED |
9/6/2023
| | 9/6/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
9/5/2023
| | 9/5/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
9/5/2023
| | 9/5/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
9/1/2023
| | 9/1/2023 | |
More Info
|
PLUMBING FINAL | REVOKE PREV APPROVAL |
8/31/2023
| | 8/31/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
CEILING | APPROVED |
8/30/2023
| | 8/30/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/29/2023
| | 8/29/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
8/29/2023
| | 8/29/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/28/2023
| | 8/28/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
8/25/2023
| | 8/25/2023 | |
More Info
|
FRAME COMM | APPROVED |
8/25/2023
| | 8/25/2023 | |
More Info
|
PLUMBING FINAL | CANCELLED |
8/24/2023
| | 8/24/2023 | |
More Info
|
FLATWORK COMM | APPROVED |
8/23/2023
| | 8/23/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
8/23/2023
| | 8/23/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
8/22/2023
| | 8/22/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
8/22/2023
| | 8/22/2023 | |
More Info
|
PLUMBING FINAL | REVOKE PREV APPROVAL |
8/22/2023
| | 8/22/2023 | |
More Info
|
ELECT FINAL COMM | APPROVED |
8/22/2023
| | 8/22/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
8/18/2023
| | 8/18/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
8/16/2023
| | 8/16/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
8/16/2023
| | 8/16/2023 | |
More Info
|
FIREINSULATION | APPROVED |
8/15/2023
| 10:00 AM | 8/15/2023 | |
More Info
|
FOOTINGS COMM | APPROVED |
8/15/2023
| | 8/15/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
8/14/2023
| | 8/14/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/14/2023
| | 8/14/2023 | |
More Info
|
CEILING | APPROVED |
8/14/2023
| | 8/14/2023 | |
More Info
|
INSULATION COMM | APPROVED |
8/14/2023
| | 8/14/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
8/11/2023
| | 8/11/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
8/9/2023
| | 8/9/2023 | |
More Info
|
FOOTINGS COMM | APPROVED |
8/8/2023
| | 8/8/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
8/2/2023
| | 8/2/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/2/2023
| | 8/2/2023 | |
More Info
|
FIREINSULATION | APPROVED |
8/2/2023
| 9:00 AM | 8/2/2023 | |
More Info
|
INSULATION COMM | APPROVED |
8/2/2023
| | 8/2/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
8/1/2023
| | 8/1/2023 | |
More Info
|
INSULATION COMM | COMM FAILED |
8/1/2023
| | 8/1/2023 | |
More Info
|
MECHANICAL FINAL | RES FAILED |
7/28/2023
| | 7/28/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/28/2023
| | 7/28/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
7/28/2023
| | 7/28/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/28/2023
| | 7/28/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
7/26/2023
| | 7/26/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/25/2023
| | 7/25/2023 | |
More Info
|
CEILING | APPROVED |
7/25/2023
| | 7/25/2023 | |
More Info
|
PLUMBING TOP OUT | APPROVED |
7/24/2023
| | 7/24/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/21/2023
| | 7/21/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
7/21/2023
| | 7/21/2023 | |
More Info
|
MECHANICAL ROUGH | RES FAILED |
7/20/2023
| | 7/20/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/20/2023
| | 7/20/2023 | |
More Info
|
FRAME COMM | APPROVED |
7/20/2023
| | 7/20/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
7/19/2023
| | 7/19/2023 | |
More Info
|
SLAB COMM | APPROVED |
7/18/2023
| | 7/18/2023 | |
More Info
|
FIREINSULATION | APPROVED |
7/18/2023
| 11:00 AM | 7/18/2023 | |
More Info
|
INSULATION COMM | APPROVED |
7/18/2023
| | 7/18/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
7/18/2023
| | 7/18/2023 | |
More Info
|
FRAME COMM | APPROVED |
7/14/2023
| | 7/14/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
7/12/2023
| | 7/12/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
7/11/2023
| | 7/11/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
7/11/2023
| | 7/11/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
7/11/2023
| | 7/11/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
7/10/2023
| | 7/10/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/10/2023
| | 7/10/2023 | |
More Info
|
INSULATION COMM | APPROVED |
7/10/2023
| | 7/10/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/7/2023
| | 7/7/2023 | |
More Info
|
INSULATION COMM | APPROVED |
7/7/2023
| | 7/7/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
7/6/2023
| | 7/6/2023 | |
More Info
|
WATER REGISTER | APPROVED |
7/6/2023
| 8:00 AM | 7/6/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/6/2023
| | 7/6/2023 | |
More Info
|
FIREINSULATION | APPROVED |
7/6/2023
| 1:30 PM | 7/6/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
7/6/2023
| | 7/6/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
7/3/2023
| | 7/3/2023 | |
More Info
|
CEILING | APPROVED |
7/3/2023
| | 7/3/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/3/2023
| | 7/3/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
7/3/2023
| | 7/3/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/30/2023
| | 6/30/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
6/29/2023
| | 6/29/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
6/28/2023
| | 6/28/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/28/2023
| | 6/28/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/26/2023
| | 6/26/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/26/2023
| | 6/26/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
6/22/2023
| | 6/22/2023 | |
More Info
|
FRAME COMM | APPROVED |
6/22/2023
| | 6/22/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
6/22/2023
| | 6/22/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
6/21/2023
| | 6/21/2023 | |
More Info
|
CEILING | APPROVED |
6/20/2023
| | 6/20/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
6/15/2023
| | 6/15/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/15/2023
| | 6/15/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
6/13/2023
| | 6/13/2023 | |
More Info
|
CEILING | APPROVED |
6/13/2023
| | 6/13/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/13/2023
| | 6/13/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
6/12/2023
| | 6/12/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
6/12/2023
| | 6/12/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/8/2023
| | 6/8/2023 | |
More Info
|
FRAME COMM | APPROVED |
6/7/2023
| | 6/7/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
6/7/2023
| | 6/7/2023 | |
More Info
|
FIREINSULATION | APPROVED |
6/7/2023
| 9:00 AM | 6/7/2023 | |
More Info
|
INSULATION COMM | APPROVED |
6/7/2023
| | 6/7/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/6/2023
| | 6/6/2023 | |
More Info
|
PLUMB TOP OUT COMM | RES FAILED |
6/6/2023
| | 6/6/2023 | |
More Info
|
WATER REGISTER | APPROVED |
6/6/2023
| 7:30 AM | 6/6/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/6/2023
| | 6/6/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/6/2023
| | 6/6/2023 | |
More Info
|
INSULATION COMM | CANCELLED |
6/6/2023
| | 6/6/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
6/6/2023
| | 6/6/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
6/2/2023
| | 6/2/2023 | |
More Info
|
INSULATION COMM | APPROVED |
6/2/2023
| | 6/2/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
6/1/2023
| | 6/1/2023 | |
More Info
|
INSULATION COMM | APPROVED |
6/1/2023
| | 6/1/2023 | |
More Info
|
DRYWALL COMM | CANCELLED |
5/31/2023
| | 5/31/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
5/30/2023
| | 5/30/2023 | |
More Info
|
INSULATION COMM | PARTIAL APPROVAL |
5/30/2023
| | 5/30/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
5/26/2023
| | 5/26/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
5/26/2023
| | 5/26/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
5/26/2023
| | 5/26/2023 | |
More Info
|
FRAME COMM | CANCELLED |
5/26/2023
| | 5/26/2023 | |
More Info
|
INSULATION COMM | APPROVED |
5/26/2023
| | 5/26/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
5/25/2023
| | 5/25/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
5/25/2023
| | 5/25/2023 | |
More Info
|
MECHANICAL ROUGH | COMM FAILED |
5/24/2023
| | 5/24/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
5/24/2023
| | 5/24/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
5/24/2023
| | 5/24/2023 | |
More Info
|
PLUMB TOP OUT COMM | RES FAILED |
5/23/2023
| | 5/23/2023 | |
More Info
|
FOOTINGS COMM | APPROVED |
5/23/2023
| | 5/23/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
5/19/2023
| | 5/19/2023 | |
More Info
|
FIREINSULATION | APPROVED |
5/19/2023
| 11:00 AM | 5/15/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
5/19/2023
| | 5/19/2023 | |
More Info
|
INSULATION COMM | CANCELLED |
5/19/2023
| | 5/19/2023 | |
More Info
|
INSULATION COMM | APPROVED |
5/18/2023
| | 5/18/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
5/18/2023
| | 5/18/2023 | |
More Info
|
BRICKWALL TIE COMM | COMM FAILED |
5/18/2023
| | 5/18/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/16/2023
| | 5/16/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
5/16/2023
| | 5/16/2023 | |
More Info
|
CEILING | APPROVED |
5/16/2023
| | 5/16/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
5/16/2023
| | 5/16/2023 | |
More Info
|
BRICKWALL TIE COMM | COMM FAILED |
5/15/2023
| | 5/15/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
5/15/2023
| | 5/15/2023 | |
More Info
|
FIREINSULATION | |
5/15/2023
| 11:30 AM | | |
More Info
|
SHEATHING COMM | APPROVED |
5/15/2023
| | 5/15/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
5/15/2023
| | 5/15/2023 | |
More Info
|
BRICKWALL TIE COMM | COMM FAILED |
5/15/2023
| | 5/15/2023 | |
More Info
|
INSULATION COMM | APPROVED |
5/12/2023
| | 5/12/2023 | |
More Info
|
FIREINSULATION | CANCELLED |
5/12/2023
| 8:00 AM | 5/12/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
5/12/2023
| | 5/12/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/12/2023
| | 5/12/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
5/11/2023
| | 5/11/2023 | |
More Info
|
FRAME COMM | APPROVED |
5/11/2023
| | 5/11/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/11/2023
| | 5/11/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
5/11/2023
| | 5/11/2023 | |
More Info
|
FRAME COMM | APPROVED |
5/9/2023
| | 5/9/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
5/8/2023
| | 5/8/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
5/5/2023
| | 5/5/2023 | |
More Info
|
PLUMB TOP OUT COMM | RES FAILED |
5/5/2023
| | 5/5/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
5/4/2023
| | 5/4/2023 | |
More Info
|
INSULATION COMM | APPROVED |
5/4/2023
| | 5/4/2023 | |
More Info
|
FIREINSULATION | APPROVED |
5/3/2023
| 1:30 PM | 5/3/2023 | |
More Info
|
FIREINSULATION | APPROVED |
5/3/2023
| 7:00 AM | 5/3/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/2/2023
| | 5/2/2023 | |
More Info
|
INSULATION COMM | APPROVED |
5/2/2023
| | 5/2/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/1/2023
| | 5/1/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
5/1/2023
| | 5/1/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
5/1/2023
| | 5/1/2023 | |
More Info
|
CEILING | APPROVED |
5/1/2023
| | 5/1/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
4/28/2023
| | 4/28/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
4/28/2023
| | 4/28/2023 | |
More Info
|
FRAME COMM | APPROVED |
4/28/2023
| | 4/28/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
4/27/2023
| | 4/27/2023 | |
More Info
|
FRAME COMM | APPROVED |
4/27/2023
| | 4/27/2023 | |
More Info
|
FRAME COMM | CANCELLED |
4/26/2023
| | 4/26/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
4/26/2023
| | 4/26/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
4/25/2023
| | 4/25/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
4/25/2023
| | 4/25/2023 | |
More Info
|
FRAME COMM | APPROVED |
4/25/2023
| | 4/25/2023 | |
More Info
|
FIREINSULATION | APPROVED |
4/24/2023
| 1:30 PM | 4/24/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
4/24/2023
| | 4/24/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
4/24/2023
| | 4/24/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
4/21/2023
| | 4/21/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
4/21/2023
| | 4/21/2023 | |
More Info
|
INSULATION COMM | APPROVED |
4/21/2023
| | 4/21/2023 | |
More Info
|
FIREINSULATION | APPROVED |
4/20/2023
| 1:30 PM | 4/20/2023 | |
More Info
|
INSULATION COMM | APPROVED |
4/20/2023
| | 4/20/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
4/19/2023
| | 4/19/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
4/19/2023
| | 4/19/2023 | |
More Info
|
DRYWALL COMM | CANCELLED |
4/18/2023
| | 4/18/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
4/18/2023
| | 4/18/2023 | |
More Info
|
BRICKWALL TIE COMM | CANCELLED |
4/17/2023
| | 4/17/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
4/14/2023
| | 4/14/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
4/14/2023
| | 4/14/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
4/13/2023
| | 4/13/2023 | |
More Info
|
FRAME COMM | APPROVED |
4/13/2023
| | 4/13/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
4/12/2023
| | 4/12/2023 | |
More Info
|
FIREINSULATION | APPROVED |
4/12/2023
| 11:00 AM | 4/12/2023 | |
More Info
|
FRAME COMM | PARTIAL APPROVAL |
4/12/2023
| | 4/12/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
4/12/2023
| | 4/12/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
4/11/2023
| | 4/11/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
4/11/2023
| | 4/11/2023 | |
More Info
|
INSULATION COMM | APPROVED |
4/11/2023
| | 4/11/2023 | |
More Info
|
CEILING | APPROVED |
4/11/2023
| | 4/11/2023 | |
More Info
|
INSULATION COMM | APPROVED |
4/10/2023
| | 4/10/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
4/10/2023
| | 4/10/2023 | |
More Info
|
ELECT ROUGH COMM | COMM FAILED |
4/10/2023
| | 4/10/2023 | |
More Info
|
FRAME COMM | APPROVED |
4/10/2023
| | 4/10/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
4/5/2023
| | 4/5/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
4/5/2023
| | 4/5/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
4/4/2023
| | 4/4/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
4/4/2023
| | 4/4/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
4/3/2023
| | 4/3/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
3/31/2023
| | 3/31/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
3/31/2023
| | 3/31/2023 | |
More Info
|
FIREINSULATION | APPROVED |
3/31/2023
| 11:00 AM | 3/31/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
3/31/2023
| | 3/31/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
3/31/2023
| | 3/31/2023 | |
More Info
|
INSULATION COMM | APPROVED |
3/31/2023
| | 3/31/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
3/31/2023
| | 3/31/2023 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
3/30/2023
| | 3/30/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
3/30/2023
| | 3/30/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
3/30/2023
| | 3/30/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
3/30/2023
| | 3/30/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
3/30/2023
| | 3/30/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
3/28/2023
| | 3/28/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
3/28/2023
| | 3/28/2023 | |
More Info
|
FIREINSULATION | APPROVED |
3/24/2023
| 8:00 AM | 3/24/2023 | |
More Info
|
FIREINSULATION | |
3/24/2023
| 8:00 AM | | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/24/2023
| | 3/24/2023 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
3/24/2023
| | 3/24/2023 | |
More Info
|
CEILING | APPROVED |
3/24/2023
| | 3/24/2023 | |
More Info
|
INSULATION COMM | PARTIAL APPROVAL |
3/23/2023
| | 3/23/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
3/23/2023
| | 3/23/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
3/23/2023
| | 3/23/2023 | |
More Info
|
SET 2 T-10 METER | APPROVED |
3/23/2023
| 9:15 AM | 3/24/2023 | |
More Info
|
SET 2 T-10 METER | APPROVED |
3/23/2023
| 10:15 AM | 6/5/2023 | |
More Info
|
SET 2 T-10 METER | APPROVED |
3/23/2023
| 1:00 PM | 3/24/2023 | |
More Info
|
SET 2 T-10 METER | APPROVED |
3/23/2023
| 9:00 AM | 3/24/2023 | |
More Info
|
METER PAYMENT | APPROVED |
3/22/2023
| | 3/22/2023 | |
More Info
|
METER PAYMENT | APPROVED |
3/22/2023
| | 3/22/2023 | |
More Info
|
METER PAYMENT | APPROVED |
3/22/2023
| | 3/22/2023 | |
More Info
|
DRYWALL COMM | COMM FAILED |
3/22/2023
| | 3/22/2023 | |
More Info
|
METER PAYMENT | APPROVED |
3/22/2023
| | 3/22/2023 | |
More Info
|
PLUMB TOP OUT COMM | COMM FAILED |
3/21/2023
| | 3/21/2023 | |
More Info
|
PAVING | APPROVED |
3/20/2023
| | 3/20/2023 | |
More Info
|
BRICKWALL TIE COMM | CANCELLED |
3/20/2023
| | 3/20/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/16/2023
| | 3/16/2023 | |
More Info
|
CEILING | APPROVED |
3/16/2023
| | 3/16/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
3/14/2023
| | 3/14/2023 | |
More Info
|
FRAME COMM | APPROVED |
3/14/2023
| | 3/14/2023 | |
More Info
|
INSULATION COMM | APPROVED |
3/13/2023
| | 3/13/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
3/13/2023
| | 3/13/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
3/13/2023
| | 3/13/2023 | |
More Info
|
FIREINSULATION | APPROVED |
3/13/2023
| 8:00 AM | 3/13/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/13/2023
| | 3/13/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
3/10/2023
| | 3/10/2023 | |
More Info
|
PLUMB TOP OUT COMM | COMM FAILED |
3/10/2023
| | 3/10/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
3/9/2023
| | 3/9/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
3/9/2023
| | 3/9/2023 | |
More Info
|
CMUWALL | APPROVED |
3/9/2023
| | 3/9/2023 | |
More Info
|
FRAME COMM | APPROVED |
3/8/2023
| | 3/8/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/3/2023
| | 3/3/2023 | |
More Info
|
FRAME COMM | COMM FAILED |
3/3/2023
| | 3/3/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
3/2/2023
| | 3/2/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/2/2023
| | 3/2/2023 | |
More Info
|
SLAB COMM | APPROVED |
3/2/2023
| | 3/2/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
3/2/2023
| | 3/2/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
3/2/2023
| | 3/2/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
3/1/2023
| | 3/1/2023 | |
More Info
|
CEILING | APPROVED |
3/1/2023
| | 3/1/2023 | |
More Info
|
MECHANICAL ROUGH | COMM FAILED |
3/1/2023
| | 3/1/2023 | |
More Info
|
CMUWALL | APPROVED |
2/24/2023
| | 2/24/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
2/24/2023
| | 2/24/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
2/22/2023
| | 2/22/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
2/22/2023
| | 2/22/2023 | |
More Info
|
PLUMB TOP OUT COMM | COMM FAILED |
2/21/2023
| | 2/21/2023 | |
More Info
|
CMUWALL | APPROVED |
2/21/2023
| | 2/21/2023 | |
More Info
|
PLUMB TOP OUT COMM | CANCELLED |
2/20/2023
| | 2/20/2023 | |
More Info
|
SLAB COMM | APPROVED |
2/17/2023
| | 2/17/2023 | |
More Info
|
CEILING | APPROVED |
2/16/2023
| | 2/16/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
2/13/2023
| | 2/13/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
2/13/2023
| | 2/13/2023 | |
More Info
|
SLAB COMM | APPROVED |
2/13/2023
| | 2/13/2023 | |
More Info
|
SLAB COMM | APPROVED |
2/13/2023
| | 2/13/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
2/13/2023
| | 2/13/2023 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
2/10/2023
| | 2/10/2023 | |
More Info
|
PAVING | APPROVED |
1/30/2023
| | 1/30/2023 | |
More Info
|
PAVING | APPROVED |
1/24/2023
| | 1/24/2023 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
1/23/2023
| | 1/23/2023 | |
More Info
|
SLAB COMM | APPROVED |
1/23/2023
| | 1/23/2023 | |
More Info
|
SLAB COMM | APPROVED |
1/20/2023
| | 1/20/2023 | |
More Info
|
SLAB COMM | APPROVED |
1/19/2023
| | 1/19/2023 | |
More Info
|
PAVING | APPROVED |
1/19/2023
| | 1/19/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
1/17/2023
| | 1/17/2023 | |
More Info
|
SHEATHING COMM | APPROVED |
1/17/2023
| | 1/17/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
1/10/2023
| | 1/10/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
1/6/2023
| | 1/6/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
1/4/2023
| | 1/4/2023 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
12/21/2022
| | 12/21/2022 | |
More Info
|
FRAME COMM | APPROVED |
12/21/2022
| | 12/21/2022 | |
More Info
|
SHEATHING COMM | APPROVED |
12/16/2022
| | 12/16/2022 | |
More Info
|
SET 2 T-10 METER | APPROVED |
12/12/2022
| 9:45 AM | 12/12/2022 | |
More Info
|
SET 2 T-10 METER | APPROVED |
12/12/2022
| 10:30 AM | 12/12/2022 | |
More Info
|
SET 2 T-10 METER | APPROVED |
12/12/2022
| 11:00 AM | 12/12/2022 | |
More Info
|
METER PAYMENT | APPROVED |
12/9/2022
| | 12/9/2022 | |
More Info
|
METER PAYMENT | APPROVED |
12/9/2022
| | 12/9/2022 | |
More Info
|
METER PAYMENT | APPROVED |
12/9/2022
| | 12/9/2022 | |
More Info
|
METER PAYMENT | APPROVED |
12/9/2022
| | 12/9/2022 | |
More Info
|
T-POLE COMM | APPROVED |
11/17/2022
| | 11/17/2022 | |
More Info
|
T-POLE COMM | APPROVED |
11/15/2022
| | 11/15/2022 | |
More Info
|
T-POLE COMM | APPROVED |
11/15/2022
| | 11/15/2022 | |
More Info
|
T-POLE COMM | APPROVED |
11/15/2022
| | 11/15/2022 | |
More Info
|
T-POLE COMM | COMM FAILED |
11/15/2022
| | 11/15/2022 | |
More Info
|
T-POLE COMM | APPROVED |
11/15/2022
| | 11/15/2022 | |
More Info
|
FRAME COMM | CANCELLED |
11/3/2022
| 8:00 AM | 11/3/2022 | |
More Info
|
SLAB COMM | APPROVED |
11/1/2022
| | 11/1/2022 | |
More Info
|
SLAB COMM | APPROVED |
11/1/2022
| | 11/1/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
11/1/2022
| | 11/1/2022 | |
More Info
|
SLAB COMM | CANCELLED |
10/28/2022
| | 10/28/2022 | |
More Info
|
SLAB COMM | CANCELLED |
10/28/2022
| | 10/28/2022 | |
More Info
|
SLAB COMM | APPROVED |
10/18/2022
| | 10/18/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
10/18/2022
| | 10/18/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
10/6/2022
| | 10/6/2022 | |
More Info
|
SLAB COMM | APPROVED |
10/5/2022
| | 10/5/2022 | |
More Info
|
SLAB COMM | APPROVED |
10/5/2022
| | 10/5/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
10/3/2022
| | 10/3/2022 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
10/3/2022
| | 10/3/2022 | |
More Info
|
SLAB COMM | APPROVED |
10/3/2022
| | 10/3/2022 | |
More Info
|
SLAB COMM | APPROVED |
9/30/2022
| | 9/30/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/30/2022
| | 9/30/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/28/2022
| | 9/28/2022 | |
More Info
|
CMUWALL | APPROVED |
9/27/2022
| | 9/27/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/26/2022
| | 9/26/2022 | |
More Info
|
FIRELANE INSPECTION | APPROVED |
9/23/2022
| 2:30 PM | 9/23/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
9/22/2022
| | 9/22/2022 | |
More Info
|
SLAB COMM | APPROVED |
9/22/2022
| | 9/22/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/20/2022
| | 9/20/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/16/2022
| | 9/16/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
9/15/2022
| | 9/15/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/14/2022
| | 9/14/2022 | |
More Info
|
SLAB COMM | APPROVED |
9/9/2022
| | 9/9/2022 | |
More Info
|
SLAB COMM | APPROVED |
9/9/2022
| | 9/9/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
9/1/2022
| | 9/1/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
8/31/2022
| | 8/31/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
8/30/2022
| | 8/30/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/26/2022
| | 8/26/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/26/2022
| | 8/26/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/26/2022
| | 8/26/2022 | |
More Info
|
PAVING | APPROVED |
8/19/2022
| | 8/19/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/17/2022
| | 8/17/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/16/2022
| | 8/16/2022 | |
More Info
|
PAVING | APPROVED |
8/15/2022
| | 8/15/2022 | |
More Info
|
SLAB COMM | CANCELLED |
8/11/2022
| | 8/11/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/11/2022
| | 8/11/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
8/11/2022
| | 8/11/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/9/2022
| | 8/9/2022 | |
More Info
|
PAVING | APPROVED |
8/9/2022
| | 8/9/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/4/2022
| | 8/4/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
8/4/2022
| | 8/4/2022 | |
More Info
|
PAVING | APPROVED |
8/1/2022
| | 8/1/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
8/1/2022
| | 8/1/2022 | |
More Info
|
SLAB COMM | APPROVED |
8/1/2022
| | 8/1/2022 | |
More Info
|
PAVING | APPROVED |
7/28/2022
| | 7/28/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/25/2022
| | 7/25/2022 | |
More Info
|
TILT WALL PANELS | APPROVED |
7/25/2022
| | 7/25/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/22/2022
| | 7/22/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/22/2022
| | 7/22/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
7/21/2022
| | 7/21/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
7/21/2022
| | 7/21/2022 | |
More Info
|
PLUMBING ROUGH-IN | CANCELLED |
7/21/2022
| | 7/21/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/15/2022
| | 7/15/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/15/2022
| | 7/15/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
7/15/2022
| | 7/15/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
7/11/2022
| | 7/11/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
6/29/2022
| | 6/29/2022 | |
More Info
|
SLAB COMM | APPROVED |
6/27/2022
| | 6/27/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
6/24/2022
| | 6/24/2022 | |
More Info
|
SLAB COMM | APPROVED |
6/22/2022
| | 6/22/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
6/17/2022
| | 6/17/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
6/17/2022
| | 6/17/2022 | |
More Info
|
BRICKWALL TIE COMM | CANCELLED |
6/14/2022
| | 6/14/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
6/13/2022
| | 6/13/2022 | |
More Info
|
PLUMBING ROUGH-IN | RES FAILED |
6/10/2022
| | 6/10/2022 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
6/9/2022
| | 6/9/2022 | |
More Info
|
T-POLE COMM | APPROVED |
6/8/2022
| | 6/8/2022 | |
More Info
|
T-POLE COMM | CANCELLED |
6/3/2022
| | 6/3/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
6/1/2022
| | 6/1/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
5/23/2022
| | 5/23/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
5/19/2022
| | 5/19/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
5/13/2022
| | 5/13/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
5/13/2022
| | 5/13/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
5/12/2022
| | 5/12/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
5/12/2022
| | 5/12/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
5/10/2022
| | 5/10/2022 | |
More Info
|
ELECT ROUGH COMM | COMM FAILED |
4/29/2022
| | 4/29/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
4/29/2022
| | 4/29/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
4/27/2022
| | 4/27/2022 | |
More Info
|
FOOTINGS COMM | APPROVED |
4/22/2022
| | 4/22/2022 | |
More Info
|
There are currently no reviews on this record.